Active

Remote ID
1
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.06.03.02
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of Namibia section of the 400kV Angola-Namibia transmission interconnector. The interconnector is expected to link the electricity networks in the north-western part of Namibia and the southern part of Angola and initially supply power to towns in southern Angola mainly Xangongo, Cahama and Ondjiva. This transmission line will also make provision for the integration of the proposed Baynes Hydro Power Station into the NamPower and RNT electricity networks.
Description

<p>The project is code named "ANNA" meaning the interconnection between Angola and Namibia. The proposed interconnector involves the construction of power transmission routed via the proposed Baynes Hydropower Plant in Lower Kunene, Namibia, to link the Namibian and Angolan electricity networks in the north western part of Namiiba and the southern part of Angola. </p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Project Risk

<p><br></p>

Countries
Namibia, Angola, Namibia, Angola, Namibia
Beneficiary Countries
Angola, Namibia
REC
SADC
Stakeholders
Angola - Rede Nacionale de Transporte de Electricidade
Angola Cables
Namibia - Ministry of Mines and Energy
Namibia Power
NEPAD Infrastructure Project Preparation Facility
Southern African Development Community
Southern African Power Pool
Email
jannis.perzlmeier@giz.de
Start Date
Date Created Raw
Updated Date
Latitude
-17.330000
Longitude
16.875000
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.06.03.01
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of Namibia section of the 400 kV Angola-Namibia transmission interconnector. The interconnector is expected to link the electricity networks in the north-western part of Namibia and the southern part of Angola and initially supply power to towns in southern Angola mainly Xangongo, Cahama and Ondjiva. This transmission line will also make provision for the integration of the proposed Baynes Hydro Power Station into the NamPower and RNT electricity networks.</p>
<p> </p>
Description

<p>The proposed interconnector involves the construction of power transmission lines from the proposed Baynes Hydropower Plant in Lower Kunene, Namibia, to link to the national power grid of Angola. While this leg of the&Acirc; project focuses on the section in Angola, it forms part of the broader project which is in Namibia.</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Project Risk

<ul>
<li> </li>
</ul>

Countries
Angola, Angola, Namibia, Angola, Namibia
Beneficiary Countries
Angola, Namibia
REC
SADC
Stakeholders
Southern African Development Community
Angola - Empresa Nacional de Electricidade de Angola
Southern African Power Pool
Angola Cables
Angola - Rede Nacionale de Transporte de Electricidade
Email
edmoyo@sadc.int
Start Date
Date Created Raw
Updated Date
Latitude
-11.880000
Longitude
43.872200
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.12.03.03
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of road and bridge from Anejo to Hillakondji (Ghana).
Description

Upgrading of road and bridge from Anejo to Hillakondji (Ghana).

Capex Cost
0.00USD million
Preparation Cost
0.00
Countries
Ghana, Ghana, Ghana
Beneficiary Countries
Ghana
REC
ECOWAS-CEDEAO
Stakeholders
Economic Community of West African States
Ghana Highway Authority
Email
ephremg@nepad.org
Updated Date
Latitude
0.000000
Longitude
0.000000
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
TBC
Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Central African Republic, Central African Republic, Democratic Republic of Congo, Republic of Congo, Angola, Burundi, Cameroon, Central African Republic, Democratic Republic of Congo, Equatorial Guinea, Gabon, Republic of Congo, Rwanda
Beneficiary Countries
Central African Republic, Democratic Republic of Congo, Republic of Congo
Stakeholders
African Union Development Agency
Email
nguena.kitio1996@gmail.com
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
TBC
Description

<span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">Suite A  l'organisation de la table ronde des bailleurs de fonds du secteur de l'Energie , A  Bruxelles en juin 2016, la CEEAC a sollicité et obtenu du Groupe de la BAD y compris IPPF/NEPAD un financement pour , entre autres, préparer de projets d'investissement. Dans le cadre de ce projet, la CEEAC est entrain d préparer pour les sites de Booué et Tsengué leledi les rapports ci-après: (i) le rapport d'avant projet sommaire de chaque barrage, (ii) le rapport d'avant projet detaillé de chaque barrage ainis que l'etude d'impavt environnemental et social assortie du Plan de Gestion Environnementale et Sociale (PGES).</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">Il est question de mobiliser les ressources pour :</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">- Préparer le Dossier d'Appel d'Offre</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">- construire:</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">a) au site de BOOUE:</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">- un barrage de prise, de caractéristiques: hauteur maximale (26 m), longueur (593 m), cA´te de retenue (173), débit d'équipement (2500 m3/s)</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">- Un canal d'amenée</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">- Une Centrale équipée de 5 groupes de type Kaplan, puissance installée: 411 MW</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">b) au site de TSENGUE-LELEDI:</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">- Un barrage de prise de caractéristiques: hauteur maximale au dessus de la fondation (44 m); longueur au couronnement (1282,6 m); cA´te de retenue (240); débit d'équipement (700 m3/s)</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">- Conduites forcées: 4</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">- Une Centrale équipée de 4 groupes de type Francis, de puissance installée de 300 MW</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">c) Lignes de Transport d'électricité vers les Etats frontaliers (Cameroun, Congo, Guinée Equatoriale)</span><br [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial;"><span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">Elles seront conçues en technologies 400 KV et constitueront les maillons des lignes d'interconnexion des réseaux électrique de l'Afrique centrale et alimenteront les zones rurales traversées directement par la ligne Haute Tension ou soit par des lignes d’interconnexion avec certaines localités ».</span><br>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Gabon, Gabon, Angola, Burundi, Cameroon, Central African Republic, Chad, Democratic Republic of Congo, Equatorial Guinea, Gabon, Republic of Congo, Rwanda
Beneficiary Countries
Gabon
Stakeholders
African Union Development Agency
Email
nguena.kitio1996@gmail.com
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 24 February 2026
PIDA Code
I.03.01
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
ICT
Subsector Name
Internet Exchange Point
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The IXP project is to keep in local internet communication local. It aims at building the technical capacity of the beneficiary country in managing Internet Exchange Point and to provide, when necessary, equipment needed for the establishment of the Internet exchange point.
Description

<p>The AXIS Project aims to facilitate the development of an African internet infrastructure through policy and regulatory reform, capacity building and technical assistance. Development of an African internet infrastructure refers to the establishment of regional internet exchange points (IXPs) and internet carriers.</p>

<p>The AXIS Project aims to facilitate the development of an African internet infrastructure through policy and regulatory reform, capacity building and technical assistance. Development of an African internet infrastructure refers to the establishment of regional internet exchange points (IXPs) and internet carriers.</p>

<p>The AXIS Project is being implemented through two phases. Phase I consists of capacity building to support the establishment of national IXPs through providing a series of two workshops for stakeholders and the Internet Service Provider Association (ISPA) on  I) best practice and benefits of IXP and II) technical assistance through workshops which will cover the technical and administrative skills needed to set up, operate, and administer an IXP.</p>

<p>Phase II focuses on supporting establishment of Regional IXP and Regional Internet Carrier through provisioning Capacity building workshops on best practice and benefits of setting up RIXP/IC and providing technical assistance.</p>

<p>The AXIS Project is a flagship project of the African Regional Action Plan on Knowledge Economy (ARAPKE) endorsed by the African Union Executive Council. </p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Algeria, Algeria, Algeria
Beneficiary Countries
Algeria
REC
UMA-AMU
Stakeholders
Arab Maghreb Union
Autorité d'Algérie de Régulation des Postes et Télécommunications
African Union Commission
Algeria - Ministry of Telecommunication
Email
ephrem.hailu@giz.de
Updated Date
Latitude
36.780000
Longitude
3.055140
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.09.01.01
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Reinforcement of the Algeria part of the 220 km / 400 kV Algeria to Tunisia section the ELTAM transmission interconnector.
Description

This project forms part of the ELTAM transmission interconnector which connects the power markets of Egypt, Libya, Tunisia, Algeria and Mali. In particular, it involves the reinforcement of the Algeria part of the 220 km / 400 kV Algeria to Tunisia section from Cheffia in Algeria to the Tunisia border.

Capex Cost
161.00USD million
Preparation Cost
17.00
Project Risk

<ul><li> Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li></ul>

Countries
Algeria, Algeria, Tunisia, Algeria, Tunisia
Beneficiary Countries
Algeria, Tunisia
REC
UMA-AMU
Stakeholders
Arab Maghreb Union
Algeria - Société Nationale de l'Électricité et du Gaz
Comité Maghrébin de l'Électricité
Email
ephremg@nepad.org
Updated Date
Latitude
36.410000
Longitude
8.023190
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Project Definition
Completion Percentage
0
Sector Name
Transport
Subsector Name
Inland Port & Waterway
Alternative Names
Kagera River, or Alexandra Nile River
Reference Plan
PIDA PAP 2
On SDM
On
Summary
Making Akagera River navigable through the construction of canals, locks, river cut offs, river improvement works (removal of rocks, islands), and river bank protection
Description

This project aims to make Akagera River navigable through the construction of canals, locks, river cut offs, river improvement works (removal of rocks, islands), and river bank protection. The entire project covers 260 km of river, from Lake Victoria to Kagitumba. River Akagera provides transport alternative that is crucial in facilitating regional trade between Rwanda, Uganda and Tanzania, which will in turn enhance regional integration.

Capex Cost
0.00USD million
Preparation Cost
0.00
Countries
Rwanda, Tanzania, Uganda
REC
EAC
Stakeholders
East African Community
Rwanda Transport Development Agency
Start Date
Date Created Raw
Latitude
-1.550000
Longitude
30.828800
By Anonymous (not verified) , 24 February 2026
PIDA Code
I.02.13.01
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
ICT
Subsector Name
Fibre Optic Cable
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of Nigeria section of fibre optic link between Abuja and Younde.
Description

<p>Data not available</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Nigeria, Cameroon, Nigeria, Cameroon, Nigeria
Beneficiary Countries
Cameroon, Nigeria
Stakeholders
African Union Development Agency
Email
ephrem.hailu@giz.de
Start Date
Date Created Raw
Updated Date
Latitude
7.310000
Longitude
8.185410
By Anonymous (not verified) , 15 February 2026
PIDA Code
I.02.13.02
Project Status
Active
Project Stage
Project Definition
Completion Percentage
0
Sector Name
ICT
Subsector Name
Fibre Optic Cable
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
*** DISCLAIMER: Project information was not obtained. It will be inserted when project information becomes available. *** Construction of Cameroun section of the fibre optic link between Abuja and Younde.
Countries
Cameroon, Nigeria, Cameroon, Nigeria, Cameroon
Beneficiary Countries
Nigeria, Cameroon
REC
ECOWAS-CEDEAO
Stakeholders
Economic Community of West African States
Nigeria - Globacom
Email
ephremg@nepad.org
Latitude
4.640000
Longitude
10.236100