<p>The proposed Kaléta dam project entails the construction of a gravity dam, with a 240 MW capacity. The Kaléta site is located in Guinea, 115 km northeast of Conakry and 130 km upstream of the mouth of the Konkouré River.</p>
<p>This project was previously part of the larger Gambia River Basin Development Organisation (OMVG) project involving the four countries, namely The Gambia, Guinea, Guinea-Bissau and Senegal. Guinea, however, decided to develop Kaléta as a stand-alone. Interconnection to other OMVG countries remains intended in future.</p>
<p>The project will have the following characteristics:</p>
<ul>
<li>Storage hydropower plant with 240 MW of hydropower capacity</li>
<li>Net average generation: 660 GWh/year</li>
<li>Gravity dam with maximum height: 22 m, crest length: 1060 m, reservoir storage: 23 million m3.</li>
</ul>