Angola Cables

By Anonymous (not verified) , 24 February 2026
PIDA Code
I.02.05.01
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
ICT
Subsector Name
Fibre Optic Cable
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of Angola section of the fibre optic link between Luanda and Lusaka.
Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Angola, Angola, Zambia, Angola, Zambia
Beneficiary Countries
Angola, Zambia
Stakeholders
Southern African Development Community
Angola Cables
Common Market for Eastern and Southern Africa
Email
gah-thew@sadc.int
Start Date
Date Created Raw
Updated Date
Latitude
-10.690000
Longitude
18.614300
By Anonymous (not verified) , 24 February 2026
PIDA Code
I.02.07.01
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
ICT
Subsector Name
Fibre Optic Cable
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
*** DISCLAIMER: Project information was not obtained. It will be inserted when project information becomes available. *** Construction of Angola section of the fibre optic link between Luanda and Kinshasa.
Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Angola, Angola, Democratic Republic of Congo, Angola, Democratic Republic of Congo
Beneficiary Countries
Angola, Democratic Republic of Congo
REC
SADC
Stakeholders
Southern African Development Community
Angola Cables
Email
gah-thew@sadc.int
Start Date
Date Created Raw
Updated Date
Latitude
-7.340000
Longitude
14.312800
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.06.03.02
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of Namibia section of the 400kV Angola-Namibia transmission interconnector. The interconnector is expected to link the electricity networks in the north-western part of Namibia and the southern part of Angola and initially supply power to towns in southern Angola mainly Xangongo, Cahama and Ondjiva. This transmission line will also make provision for the integration of the proposed Baynes Hydro Power Station into the NamPower and RNT electricity networks.
Description

<p>The project is code named "ANNA" meaning the interconnection between Angola and Namibia. The proposed interconnector involves the construction of power transmission routed via the proposed Baynes Hydropower Plant in Lower Kunene, Namibia, to link the Namibian and Angolan electricity networks in the north western part of Namiiba and the southern part of Angola. </p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Project Risk

<p><br></p>

Countries
Namibia, Angola, Namibia, Angola, Namibia
Beneficiary Countries
Angola, Namibia
REC
SADC
Stakeholders
Angola - Rede Nacionale de Transporte de Electricidade
Angola Cables
Namibia - Ministry of Mines and Energy
Namibia Power
NEPAD Infrastructure Project Preparation Facility
Southern African Development Community
Southern African Power Pool
Email
jannis.perzlmeier@giz.de
Start Date
Date Created Raw
Updated Date
Latitude
-17.330000
Longitude
16.875000
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.06.03.01
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of Namibia section of the 400 kV Angola-Namibia transmission interconnector. The interconnector is expected to link the electricity networks in the north-western part of Namibia and the southern part of Angola and initially supply power to towns in southern Angola mainly Xangongo, Cahama and Ondjiva. This transmission line will also make provision for the integration of the proposed Baynes Hydro Power Station into the NamPower and RNT electricity networks.</p>
<p> </p>
Description

<p>The proposed interconnector involves the construction of power transmission lines from the proposed Baynes Hydropower Plant in Lower Kunene, Namibia, to link to the national power grid of Angola. While this leg of the&Acirc; project focuses on the section in Angola, it forms part of the broader project which is in Namibia.</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Project Risk

<ul>
<li> </li>
</ul>

Countries
Angola, Angola, Namibia, Angola, Namibia
Beneficiary Countries
Angola, Namibia
REC
SADC
Stakeholders
Southern African Development Community
Angola - Empresa Nacional de Electricidade de Angola
Southern African Power Pool
Angola Cables
Angola - Rede Nacionale de Transporte de Electricidade
Email
edmoyo@sadc.int
Start Date
Date Created Raw
Updated Date
Latitude
-11.880000
Longitude
43.872200