Southern African Development Community

By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.05.02
Project Status
Active
Project Stage
Construction
Completion Percentage
1
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of Malawi section approximately 200 km of 400 kV (initial operation at 220 kV) Mozambique-Malawi transmission interconnector, which will connect Malawi to the Southern Africa Power Pool (SAPP).
Description

<p>The project entails the construction of a 200 km, 400 kV(initially 220 kV) power line from Matambo substation, in Mozambique, to Phombeya, north of Blantyre. The first assignment will involve the design, supply and installation of the 400 kV overhead transmission line from the Mozambique-Malawi border to a new substation at Phombeya. The second assignment will entail the design, supply and installation of the new 400 kV Phombeya substation. Other assignments include extension of Matambo substation (Mozambique) and upgrading of SCADA systems (EDM).</p>

Capex Cost
0.00USD million
Preparation Cost
2.00
Operation Cost
120.00
Project Risk

<ul><li></li></ul>

Countries
Malawi, Malawi, Mozambique, Malawi, Mozambique
Beneficiary Countries
Malawi, Mozambique
REC
SADC
Stakeholders
Malawi - Electricity Supply Corporation of Malawi
Malawi - Ministry of Natural Resources
Energy and Mining
Mozambique - Electricidade de Mocambique
Southern African Development Community
Southern African Power Pool
World Bank
Email
jannis.perzlmeier@giz.de
Start Date
Date Created Raw
Updated Date
Latitude
-15.880000
Longitude
34.227900
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.06.02
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The Mozambique-Zambia Interconnector will consist of a high voltage transmission line from Chipata 330/132/33 kV substation to the proposed Cataxa substation in Mozambique. The transmission voltage will either be 330 kV or 400 kV. The total line length is estimated at 286 km of which 77 km is in Zambia and the rest in Mozambique.
Description

<p>Construction of a transmission line that connects Cahora Bassa Hydroelectric Power Station at Songo in Mozambique with the power system of Zambia at Serenje.</p>

Capex Cost
0.00USD million
Preparation Cost
4.60
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li></ul>

Countries
Zambia, Mozambique, Zambia, Mozambique, Zambia
Beneficiary Countries
Mozambique, Zambia
REC
SADC
Stakeholders
Mozambique - Electricidade de Mocambique
Southern African Development Community
Southern African Power Pool
Zambia - Ministry of Housing and Infrastructure Development
Zambia - Ministry of Transport and Communications
Zambia Electricity Supply Company
Zambia - Ministry of Energy
Email
egetahun@outlook.com
Start Date
Date Created Raw
Updated Date
Latitude
-14.770000
Longitude
31.970200
By Anonymous (not verified) , 24 February 2026
PIDA Code
I.03.24
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
ICT
Subsector Name
Internet Exchange Point
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The IXP project is to keep in local internet communication local. It aims at building the technical capacity of the beneficiary country in managing Internet Exchange Point and to provide, when necessary, equipment needed for the establishment of the Internet exchange point.
Description

<p>The AXIS Project aims to facilitate the development of an African internet infrastructure through policy and regulatory reform, capacity building and technical assistance. Development of an African internet infrastructure refers to the establishment of regional internet exchange points (IXPs) and internet carriers.</p>

<p>The AXIS Project is being implemented through two phases. Phase I consists of capacity building to support the establishment of national IXPs through providing a series of two workshops for stakeholders and the Internet Service Provider Association (ISPA) on  I) best practice and benefits of IXP and II) technical assistance through workshops which will cover the technical and administrative skills needed to set up, operate, and administer an IXP.</p>

<p>Phase II focuses on supporting establishment of Regional IXP and Regional Internet Carrier through provisioning Capacity building workshops on best practice and benefits of setting up RIXP/IC and providing technical assistance.</p>

<p>The AXIS Project is a flagship project of the African Regional Action Plan on Knowledge Economy (ARAPKE) endorsed by the African Union Executive Council. </p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Mauritius, Mauritius, Mauritius
Beneficiary Countries
Mauritius
REC
SADC
Stakeholders
African Union Commission
Southern African Development Community
Mauritius - Ministry of Technology
Communication and Innovation
Email
egetahun@outlook.com
Start Date
Date Created Raw
Updated Date
Latitude
-20.160000
Longitude
57.494500
By Anonymous (not verified) , 24 February 2026
PIDA Code
I.02.19.01
Project Status
Completed
Project Stage
Construction
Completion Percentage
0
Sector Name
ICT
Subsector Name
Fibre Optic Cable
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of 600 km fibre optic link between Lusaka and Lilongwe (Zambia section).
Description

<p>The project entails the installation of the Zambia section of the 600 km fibre-optic link between Lusaka and Lilongwe: from Lusaka to the border with Malawi.</p>

Capex Cost
2.00USD million
Preparation Cost
0.02
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: None Social Risks: None Socio-Enviro Classification: C - minimal social and environmental impacts Other External Risks: Not Reported</li></ul>

Countries
Zambia, Malawi, Zambia, Malawi, Zambia
Beneficiary Countries
Malawi, Zambia
Stakeholders
Africa ICT Alliances
Common Market for Eastern and Southern Africa
Zambia - Ministry of Housing and Infrastructure Development
Zambia - Ministry of Transport and Communications
Southern African Development Community
Zambia Electricity Supply Company
Email
egetahun@outlook.com
Start Date
Date Created Raw
Updated Date
Latitude
-14.520000
Longitude
30.537300
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Project Definition
Completion Percentage
0
Sector Name
Water
Subsector Name
Water Supply
Alternative Names
Not available
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
<p>Water transfer from Lesotho to South Africa, for water supply to South Africa and hydropower generation in Lesotho. </p>
Description

<p>The first-phase of the multi-phase Lesotho Highlands Water Project (LHWP) entailed the construction of Katse Dam, Mohale Dams, Matsoku Diversion Tunnel and the Muela hydropower station. Lesotho benefits from a sustainable, independent energy supply for Lesotho that will meet the country's electricity requirements and royalty revenue from the project, while South Africa benefits from the security of supply of high quality water that is transferred into the Vaal River system for domestic and industrial use in the Gauteng province. Phase II of the LHWP will be implemented in terms of two distinct components: a water delivery system to augment the delivery of water to South Africa and a hydropower generation system, which will increase the current electricity generation capacity in Lesotho. The program involves the construction of the Polihali Dam and the Transfer Tunnel in the Mokhotlong district and a hydropower scheme following the conclusion of a joint feasibility studies. As per the provisions of the Phase II Agreement between the Government of the Kingdom of Lesotho and the Republic of South Africa, the implementation of the Kobong Pump Storage scheme or any other hydro scheme was subject to the outcome of a joint feasibility studies. The technical and the economic feasibility studies for the Kobong Pump Storage scheme were completed in 2013. However, the outcome was that further studies should be undertaken. These included, a market study, an integration study, geotechnical investigations and legal and commercial arrangements Lesotho secured funding from the World Bank to undertake the above studies, including convectional hydropower options. These studies are expected to be substantially complete by the end of August 2019 . The further feasiility studies have looked at pumped storage and conventional hydropower options. The decision was taken to defer the pump storage option (due to prevailing economic conditions) and advance the conventional options. This entails one site at Oxbow on Malibamat&scaron;o River and two sites on the Senqu River. . The topography of the region allows for the possibility of developing a hydro-power generation in Lesotho in conjunction with the provision of water supplies to the RSA. For South Africa, construction of this dam and related infrastructure will guarantee the desired level of water availability in Gauteng and the Vaal River system in the most cost-effective manner. In parallel with water conservation measures in the Vaal River, it will also influence the improvement of water quality amongst many benefits. Phase II water delivery and hydropower generation are expected to be commissioned at the same time early in 2026, and the project close out is forecast for December 2028.</p>

Capex Cost
2,600.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Project Risk

<p>Not available</p>

Countries
Lesotho, South Africa
REC
SADC
Stakeholders
Lesotho - Government of Lesotho
South Africa - Government of South Africa
Southern African Development Community
Zambia - Government of Zambia
Start Date
Date Created Raw
Latitude
-11.880000
Longitude
43.872200
By Anonymous (not verified) , 24 February 2026
PIDA Code
W.04.01
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Water
Subsector Name
Multi-purpose Reservoir
On SDM
Off
Summary
In terms of infrastructure, the project involves construction of: (1) a 165 m high, concrete-faced rockfill (CFRD) embankment Polihali dam downstream of the confluence of the Orange-Senqu and Khubelu rivers, Mokhotlong district. (2) a 50-m-high saddle dam. (3) a 38 km long, 5-m-diameter Polihali-Katse dam tunnel that will transfer water from the Polihali reservoir to the Katse reservoir, (4) a hydropower scheme - The exact form of the Phase II hydropower component is still to be confirmed following the completion of further feasibility studies. The studies have looked at pumped storage and conventional hydropower options. The decision was taken to defer the pump storage option (due to prevailing economic conditions) and advance the conventional options. This entails one site at Oxbow on Malibamatšo River and two sites on the Senqu River. These studies are expected to be substantially complete by the end of June 2019 and (5) advance infrastructure such as roads, bridges, high tension power lines and telecommunications systems, accommodation and construction facilities . Water will be abstracted from the Polihali reservoir through two separate concrete bell-mouth intakes on the western side of the Polihali reservoir, in the Khubelu river, 3 km upstream of the confluence with the Senqu.

The Phase II project therefore entails the construction of the Polihali Dam; a transfer tunnel from Polihali Dam to Katse reservoir; as well as advance infrastructure, environmental and social development programs in Lesotho. Phase II will increase the current supply rate of 780-million cubic metres a year incrementally to more than 1,270 million cubic metres a year. South Africa receives 24.6m³ of water per second from the LHWP. A cumulative total of 45.5m³ per second will flow as a result of the expansion.
Description

<p>~~The first-phase of the multi-phase Lesotho Highlands Water Project (LHWP) entailed the construction of Katse Dam, Mohale Dams, Matsoku Diversion Tunnel and the Muela hydropower station.  Lesotho benefits from a sustainable, independent energy supply for Lesotho that will meet the country"’s electricity requirements and royalty revenue from the project, while South Africa benefits from the security of supply of high quality water that is transferred into the Vaal River system for  domestic and industrial use in the Gauteng province.<br>
Phase II of the LHWP will be implemented in terms of two distinct components: a water delivery system to augment the delivery of water to South Africa and a hydropower generation system, which will increase the current electricity generation capacity in Lesotho.<br>
The program involves the construction of the Polihali Dam and the Transfer Tunnel in the Mokhotlong district and a hydropower scheme following the conclusion of a joint feasibility studies.<br>
As per the provisions of the Phase II Agreement between the Government of the Kingdom of Lesotho and the Republic of South Africa, the implementation of the Kobong Pump Storage scheme or any other hydro scheme was subject to the outcome of a joint feasibility studies. The technical and the economic feasibility studies for the Kobong Pump Storage scheme were completed in 2013. However, the outcome was that further studies should be undertaken. These  included, a market study, an integration study, geotechnical investigations and legal and commercial arrangements<br>
Lesotho secured funding from the World Bank to undertake the above studies, including convectional hydropower options. These studies are expected to be substantially complete by the end of August 2019 . The further feasiility studies have looked at pumped storage and conventional hydropower options. The decision was taken to defer the pump storage option (due to prevailing economic conditions) and advance the conventional options. This entails one site at Oxbow on MalibamatÅ¡o River and two sites on the Senqu River.   .<br>
The topography of the region allows for the possibility of developing a hydro-power generation in Lesotho in conjunction with the provision of water supplies to the RSA. For South Africa, construction of this dam and related infrastructure will guarantee the desired level of water availability in Gauteng and the Vaal River system in the most cost-effective manner.  In parallel with water conservation measures in the Vaal River, it will also influence the improvement of water quality amongst many benefits.  Phase II water delivery and hydropower generation are expected to be commissioned at the same time early in 2026, and the project close out is forecast for December 2028.</p>

Capex Cost
2,600.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Project Risk

<ul><li>Two countries are involved, coordination and collaboration are required by both countries. Political risk insurance where required could add a cost to the project as well, but could be minimized through existing project governance structures. However, increase in interest rates could result in additional funding cost to the project. </li></ul>

Countries
Lesotho, Lesotho, South Africa, Lesotho, South Africa
Beneficiary Countries
Lesotho, South Africa
REC
SADC
Stakeholders
Global Water Partnership
Lesotho - Government of Lesotho
Lesotho - Ministry of Water
Lesotho Highlands Development Authority
South Africa - Government of South Africa
Southern African Development Community
Trans-Caledon Tunnel Authority
Zambia - Ministry of Water Development
Sanitation and Environmental Protection
Email
ephremg@nepad.org
Start Date
Date Created Raw
Updated Date
Latitude
-29.340000
Longitude
28.507100
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Water
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Water transfer from Lesotho to Botswana across South Africa, to meet water supply demands in Botswana, Lesotho and en route parts of South Africa. It involves construction of a multipurpose dam along Makhaleng River in Lesotho and conveyance system from Lesotho to Botswana.
Description

<p>Water transfer from Lesotho to Botswana across South Africa, to meet water supply demands in Botswana, Lesotho and en route parts of South Africa. It involves construction of a multipurpose dam along Makhaleng River in Lesotho and conveyance system from Lesotho to Botswana.</p><p>Various foreseen water uses include domestic, industrial, irrigation, hydropower generation and environmental water requirements.</p><p>Dam in Lesotho. Conveyance system in Lesotho, South Africa and Botswana</p><p>The project serves a planned infrastructure asset of another sector, but there is less than 50% overlap in the geography serviced by the proposed project and the other sector planned asset.</p><p>Although studies are ongoing, indicatively about 75% of the yield from the proposed dam in Lesotho is foreseen for water demands in Botswana.</p><p><br></p>

Capex Cost
3,000.00USD million
Preparation Cost
4.00
Operation Cost
150.20
Countries
Botswana, Lesotho, South Africa, Botswana, Lesotho, South Africa, Botswana, Lesotho, South Africa
Beneficiary Countries
Botswana, Lesotho, South Africa
REC
SADC
Stakeholders
Orange-Senqu River Commission
Southern African Development Community
Email
egetahun@outlook.com
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.04.02
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
*** DISCLAIMER: Project information is incomplete. It will be updated regularly as revisions become available. ***Construction of 1,200 MW Kobong pumped storage dam in Lesotho.
Description

The Kobong Project will consist of a 1200 mW pump storage dam and power generation facility constructed along the upper Kobong River, a tributary of the Maliba-mats"’o River which flows into the Katse Dam reservoir. The majority of the power generated at Kobong will be exported to South Africa, while 20 megawatts will be used locally in Lesotho.

Capex Cost
800.00USD million
Preparation Cost
40.00
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: Not Reported

Social Risks: Not Reported

Socio-Enviro Classification: Not Reported

Other External Risks: Not Reported</li></ul>

Countries
Lesotho, Lesotho, South Africa, Lesotho, South Africa
Beneficiary Countries
Lesotho, South Africa
REC
SADC
Stakeholders
Lesotho - Ministry of Energy and Meteorology
Lesotho Highlands Development Authority
Southern African Development Community
Southern African Power Pool
Email
egetahun@outlook.com
Start Date
Date Created Raw
Updated Date
Latitude
-29.180000
Longitude
28.481600
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Project Definition
Completion Percentage
0
Sector Name
Transport
Subsector Name
Border Post
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
add text
Description

<p>add text</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Malawi, Tanzania, Malawi, Tanzania, Malawi, Tanzania
Beneficiary Countries
Malawi, Tanzania
REC
SADC
Stakeholders
Malawi - Ministry of Transport and Public Works
Southern African Development Community
Email
ephrem.hailu@giz.de
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The project road runs North from the turn-off to Kamuzu International Airport (KIA) to the North of Lilongwe to the turn-off to the district centre of Mzimba in Northern Malawi for approximately 234 km. The road starts at KIA junction and travels North via Kasungu and Jenda where it ends at the turn-off to Mzimba Boma. The section between the KIA turn-off to Jenda was constructed in the early 1980s and a portion of this section between Chatoloma and Jenda was resealed in 2005. The road is used by both motorist and non-motorized vehicles, in particular between Lilongwe and Kasungu where there are many trading centres and towns along the route.

The regional location map below shows the importance of this link with respect to the Main Corridors of in Tripartite region, such as the North South Corridor Network. This road section comprises the important link from Lilongwe to the turn-off to Mzimba Boma, approximately 250 km to the North. Lilongwe is a strategic junction city as it joins the North South Corridor to the Nacala Road Corridor. The M1 is the backbone of Malawi road network. It facilitates regional trade and tourism with Mozambique in the South, and further beyond to other SADC countries. The road links Malawi and Zambia to the important port of Dar es Salaam and as such forms a vital link for the importation and exportation of strategic goods.

The primary economic function of the road is the long-distance transportation of goods exported from Malawi and imports for Malawi. These goods are transported through the port of Dar es Salaam in Tanzania. Fuel is the main product handled but the road also provides for the import of goods to the mining activities along the road corridor and exports from mining and agriculture. The M1 through Malawi offers the shortest import/export route to Dar es Salaam for Zambia"â„¢s agriculturally important Eastern Province. The road is also a major route from Lilongwe to the North and carries significant local traffic serving district administrative centres and trading centres along its route.
Description

<p>The project road runs North from the turn-off to Kamuzu International Airport (KIA) to the North of Lilongwe to the turn-off to the district centre of Mzimba in Northern Malawi for approximately 234 km. The road starts at KIA junction and travels North via Kasungu and Jenda where it ends at the turn-off to Mzimba Boma. The section between the KIA turn-off to Jenda was constructed in the early 1980s and a portion of this section between Chatoloma and Jenda was resealed in 2005. The road is used by both motorised and non-motorised vehicles, in particular between Lilongwe and Kasungu where there are many trading centres and towns along the route. Between Lilongwe and the Kachinda turn-off to the S113 the road traverses mainly rolling to flat terrain with several river crossings including three high level bridges. It passes the following trading centres:</p>

<ul>
<li>Lumbadzi Trading Centre</li>
<li>Mponela Trading Centre</li>
<li>Madisi Trading Centre</li>
<li>Bua Trading Centre</li>
<li>Chinkhoma Trading Centre</li>
<li>Dwangwa Trading Centre</li>
<li>Phomwa Trading Centre</li>
<li>Bowe Trading Centre</li>
<li>Chatoloma Trading Centre</li>
<li>Nkhamenya Trading Centre</li>
<li>Jenda Trading Centre</li>
</ul>

<p>North of the Kachindamoto turn-off the terrain becomes hilly and the road passes through the Chimaliro Forest Reserve before reaching Jenda. North of Jenda there are a few trading centres and settlements but with far fewer people seen on the road than South of the Kachinda turn-off and in the vicinity of Jenda. The road passes through the Vipya forest reserve before reaching the turn-of to Mzimba.</p>

Capex Cost
120.00USD million
Preparation Cost
0.62
Operation Cost
120.00
Project Risk

<ul><li>Adverse weather conditions; </li><li>High inflation and excessive interest rates; and </li><li>uncertainty about external aid flows.</li></ul>

Countries
Malawi, Malawi, Malawi, Mozambique, South Africa, Tanzania, Zambia, Zimbabwe
Beneficiary Countries
Malawi
Stakeholders
African Development Bank
Common Market for Eastern and Southern Africa
European Development Fund
Malawi - Ministry of Transport and Public Works
Southern African Development Community
Tripartite Project Preparation and Implementation Unit
African Development Bank
European Development Fund
Email
jannis.perzlmeier@giz.de
Start Date
Date Created Raw
Updated Date