Nile Equatorial Lakes Subsidiary Action Program

By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.03.03
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of 905 km single circuit bidirectional 330 kV transmission interconnector from Kabwe in Zambia to the Tanzanian border at Nakonde. In Zambia, the component of the ZTK: Kabwe - Pensulo, 298 km. A second 330 kV line is required in addition to the existing. Pensulo -Mpika, 197 km. A second 330 kV line is required in addition to the existing. Mpika - Kasama, 197 km. A second 330 kV line is required in addition to the existing. Kasama -Nakonde, 212 km. Two new 330 kV circuits required Nakonde ZM/TZ Border, New 14 km Double circuit 400 kV line required.</p>
Description

<p>Construction of a transmission line that connects the power networks of Zambia, Tanzania and Kenya. This project includes the section of 905km Zambian section of the 2,800km&Acirc; ZTK interconnector from Kabwe-Pensulo-Nakonde-Kasama in Zambia to Tunduma&Acirc; in Tanzania. The project was envisioned to be implemented in two phases starting with the Kabwe-Pensulo-Kasama-Nakonde&Acirc; section and the second phase would have&Acirc; comprised the Kabwe-Pensulo-Mpika-Kasama section. It will have had a capacity of&Acirc; 500MW, upgradable to 2000MW depending on power demand.</p>
<p>The original concept for the ZTK Interconnector was a high voltage 330 kV transmission line going from Pensulo (Zambia) to Nairobi (Kenya) with three connection points in Tanzania (Mbeya, Singida and Arusha). At that time, Tanzania grid was operated at 220 kV. The original concept of the ZTK Interconnector has been replaced, by two interconnections between two national grids: the Kenya-Tanzania Interconnection and the Zambia-Tanzania Interconnection.</p>

Capex Cost
162.00USD million
Preparation Cost
5.00
Operation Cost
3.24
Project Risk

<p>The major risks facing the interconnection project were identified and analysed.</p>
<p>Among these risks, special attention is warranted to the following categories of risks and to the measures to</p>
<p>mitigate them:</p>
<p>? Operational risks (in particular, the risks arising from organizational or technical reasons);</p>
<p>? Financial risks;</p>
<p>? Risks related to the environmental and social impacts;</p>
<p>While these risks and their impact are potentially serious, adequate mitigating measures, as indicated in</p>
<p>section 14, can reduce their likelihood of occurrence, diminish their impact, and ensure successful completion</p>
<p>and operation of the interconnection.</p>

Countries
Zambia, Kenya, Tanzania, Zambia, Kenya, Tanzania, Zambia
Beneficiary Countries
Kenya, Tanzania, Zambia
Stakeholders
African Union Development Agency
Common Market for Eastern and Southern Africa
Eastern Africa Power Pool
European Commission
Nile Equatorial Lakes Subsidiary Action Program
Southern African Development Community
Southern African Power Pool
World Bank
Zambia Electricity Supply Company
Zambia Office for the Promotion of Private Power Investment
Zambia - Ministry of Energy
European Commission
Start Date
Date Created Raw
Updated Date
Latitude
-11.150000
Longitude
31.547200
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.03.02
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of 96 km / 400 kV Kenya section of the ZTK transmission interconnector.</p>
Description

<p>Construction of a transmission line that connects the power networks of Zambia, Tanzania and Kenya. This project includes the section of 96km Kenyan section of the 2,800km ZTK interconnector&Acirc; from&Acirc; Arush in Tanzania to Isinya in Kenya. In Kenya, the line will be linked to the High Voltage Direct Current Interconnector between Kenya and Ethiopia.</p>

Capex Cost
50.00USD million
Preparation Cost
12.00
Operation Cost
0.00
Countries
Kenya, Kenya, Tanzania, Zambia, Kenya, Tanzania, Zambia, Lesotho
Beneficiary Countries
Kenya, Tanzania, Zambia
Stakeholders
African Union Development Agency
Common Market for Eastern and Southern Africa
East African Community
Eastern Africa Power Pool
Kenya Power and Lighting Company
Nile Equatorial Lakes Subsidiary Action Program
Start Date
Date Created Raw
Updated Date
Latitude
-1.290000
Longitude
36.819900
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Water
Subsector Name
Multi-purpose Reservoir
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
<p>The Angololo Water Resources Development Project (AWDP) is located on the transboundary Malaba River shared by Kenya and Uganda and falls within the Sio-Malaba Malakisi (SMM) River Basin of the Nile Basin. The project is located at coordinates 0.693243&Acirc;&deg;N, 34.306400&Acirc;&deg;E. The project consists of a proposed 30 m high dam with a reservoir capacity of 43.0 MCM and hydropower generation capacity of 1.75 MW. The dam will supply potable water to 20,000 people and irrigate 3,300 hectares (1,180 ha in Kenya and 2,120 ha in Uganda). The project also includes rehabilitation of the 430 km2 watershed upstream of the dam. In total the Angololo Water Resources Development Project is expected to benefit at least 127,300 people from Tororo, Manafwa, and Namisindwa districts in Eastern Uganda and Busia and Bungoma Counties in Kenya through employment creation, irrigated agriculture, piped water supply, hydropower generation, and livestock and fisheries production.</p>
<p>The Angololo project was identified by Kenya and Uganda in collaboration with NELSAP-CU under the Sio Malaba Malakisi (SMM) River Basin Management (RBM) project. NELSAP-CU conducted its prefeasibility studies in 2010 with grant financing from the Royal Government of Sweden and the Royal Government of Norway. Feasibility studies (including detailed designs, ESIA and RAP studies and stakeholder engagement) commenced in 2019 with a US$ 1.5 million grant from NEPAD-IPPF and are expected to reach completion in 2021.</p>
Capex Cost
67.00USD million
Preparation Cost
1.58
Operation Cost
0.00
Countries
Kenya, Uganda, Kenya, Uganda, Kenya, Uganda
Beneficiary Countries
Kenya, Uganda
Stakeholders
Nile Basin Initiative
Nile Equatorial Lakes Subsidiary Action Program
East African Community
Inter-Governmental Authority on Development (IGAD)
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.13.01
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Regional Rusumo Falls HydroelectricPower Project II</p>
Description

<p>Regional Rusumo Falls Hydroelectric Project (RRFHP) Development Objective is to increase the supply of electricity to the national grids of Rwanda, Tanzania and Burundi. It Comprises of construction of an 80 MW power plant including the associated generation substation. The project is jointly financed by&Acirc; the Governments of Rwanda, Burundi and Tanzania with credits and grants totaling to USD 340&Acirc; million equivalent for the Civil Works and Electromechanical Works. AfDB parallel-financing is associated with the transmission lines to each of the three countries at a cost of USD 121 Million.&Acirc; These include 220kV transmission lines double circuit running 161 km from the power plant to Gitega substation in Burundi, 119km double circuit line from the Power plant to Shango sub-station in Rwanda and 98.2 km double circuit line from the power plant to Nyakanazi sub-station in Tanzania.The project has the following components CP1 (Civil Works); CP2 (Electromechanical works); Livelihoods Restoration Program (LRP); and Local Area Development Program (LADP). Out of the USD 340 million, the budget breakdown for each of the component is as follows: (i)LADP allocation is USD&Acirc; 15 million (USD 5 million for each country (Burundi, Rwanda and Tanzania); (ii)LRP allocation is about USD&Acirc; 711,612 (only for PAPs); and (iii)The remaining is for CP1, CP2, OE, and PIU operations.The three governments mandated and entrusted Nile Basin Initiative /Nile Equatorial lakes Subsidiary Action Program Coordination Unit (NBI/NELSAP CU) to coordinate the implementation of the project. The Nile Basin Trust Fund (NBTF) financed the Feasibility and Design Studies to a tune of USD 7.72 million. The studies were carried out from 2005 and completed in 2013. The studies were undertaken by NBI/NELSAP CU. The Project was approved by the World Bank in 2014; procurement of CP1 Contractor and CP2 Contractor was started in 2015 and completed and Contracts signed on 9th November, 2016; mobilization for construction works started in December 2016/January 2017; and the project completion date is 2021.</p>
<p> </p>

Capex Cost
461.00USD million
Preparation Cost
7.72
Operation Cost
0.00
Project Risk

<ul>
<li>Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li>
</ul>

Countries
Rwanda, Tanzania, Burundi, Rwanda, Tanzania, Burundi, Rwanda, Tanzania
Beneficiary Countries
Burundi, Rwanda, Tanzania
REC
EAC
Stakeholders
East African Community
Nile Equatorial Lakes Subsidiary Action Program
Rusumo Power Company Limited
Nile Equatorial Lakes Subsidiary Action Program
Start Date
Date Created Raw
Updated Date
Latitude
-2.380000
Longitude
30.784300
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Project Definition
Completion Percentage
0
Sector Name
Water
Subsector Name
Multi-purpose Reservoir
Alternative Names
Not available
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
<p>In total the Angololo Water Resources Development Project is expected to benefit at least 127,300 people from Tororo, Manafwa, and Namisindwa districts in Eastern Uganda and Busia and Bungoma Counties in Kenya through employment creation, irrigated agriculture, piped water supply, hydropower generation, and livestock and fisheries production. </p>
Description

<p>The Angololo Water Resources Development Project (AWDP) is located on the trans-boundary Malaba River that is between Kenya and Uganda and it falls within the Sio-Malaba Malakisi (SMM) River Basin within the Lake Victoria sub basin. The Angololo project was identified by Kenya and Uganda in collaboration with Nile Equatorial Lakes Subsidiary Action Program (NELSAP) through its Sio Malaba Malakisi (SMM) River Basin Management (RBM) project. NELSAP-CU conducted its prefeasibility studies in 2010 with grant financing from the Royal Government of Sweden and the Royal Government of Norway. Following this identification study, the Governments of Kenya and Uganda formally requested NELSAP to integrate it into its pipeline of natural resources projects for further appraising and development. The project was approved during the 18th Nile Equatorial Lakes Council of Ministers (NELCOM) meeting held in Entebbe, Uganda on 13th October 2015 and was included into the African Development Bank (AfDB) pipeline (IOP) for the year 2016 &ndash; 18 to seek possible funding support. NELSAPCU/NBI was mandated in the signed MOU between Uganda and Kenya to support in mobilization of resources for preparation of the investment project. NELSAPCU approached AfDB Eastern Africa Regional Centre (EARC) for funding to undertake preparation studies. The project studies will consist of the following components: &bull; Feasibility Study, Detailed Design and Preparation of Tender Documents; &bull; Independent Environmental and Social Impact Assessment (ESIA) and Resettlement Action Plan (RAP) &bull; Stakeholder engagements to validate project study outputs. Once proven economically viable, the project studies will proceed to Detailed Designs (DD), and preparation of tender documents.</p>

Capex Cost
60.00USD million
Operation Cost
0.00
Project Risk

<p>1. Political risk: Both Kenya and Uganda have relatively stable political environments. However, potential policy and regulatory changes may occur due to an increased political efforts to expand government programs and manage debt sustainability, which could potentially affect implementation of the project.</p>
<p>2. Procurement and Implementation Delay risk: One of the majorpotentialrisks tothe project is the timely completion and delivery of outputs that could arise from procurement and implementation delays. This risk could derail the implementation schedule due to lengthy conclusion of procurement activitiesleading to award of contract to the successful firm. Delays could also be experienced during implementation of studies, potentially due to delays in access to sites, approval or data. Often times in regional project such as this one, validation of reports and issuance of approval of outputs can also be a source of delays as consensus will be required from both countries and other stakeholders. (Project Information Memorandum - Angololo Multipurpose Water Resources Development Project&ndash;Feasibility Studies, Detailed Design, Preparation of Tender Documents, ESIAand RAP, NEPAD -Infrastructure Project Preparation Facility (NEPAD &ndash;IPPF), October2018</p>

Countries
Kenya, Uganda
REC
IGAD
Stakeholders
Uganda - Government of Uganda
Nile Equatorial Lakes Subsidiary Action Program
Inter-Governmental Authority on Development (IGAD)
Start Date
Date Created Raw
Latitude
0.670000
Longitude
34.272600