Eastern Africa Power Pool

By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.03.03
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of 905 km single circuit bidirectional 330 kV transmission interconnector from Kabwe in Zambia to the Tanzanian border at Nakonde. In Zambia, the component of the ZTK: Kabwe - Pensulo, 298 km. A second 330 kV line is required in addition to the existing. Pensulo -Mpika, 197 km. A second 330 kV line is required in addition to the existing. Mpika - Kasama, 197 km. A second 330 kV line is required in addition to the existing. Kasama -Nakonde, 212 km. Two new 330 kV circuits required Nakonde ZM/TZ Border, New 14 km Double circuit 400 kV line required.</p>
Description

<p>Construction of a transmission line that connects the power networks of Zambia, Tanzania and Kenya. This project includes the section of 905km Zambian section of the 2,800km&Acirc; ZTK interconnector from Kabwe-Pensulo-Nakonde-Kasama in Zambia to Tunduma&Acirc; in Tanzania. The project was envisioned to be implemented in two phases starting with the Kabwe-Pensulo-Kasama-Nakonde&Acirc; section and the second phase would have&Acirc; comprised the Kabwe-Pensulo-Mpika-Kasama section. It will have had a capacity of&Acirc; 500MW, upgradable to 2000MW depending on power demand.</p>
<p>The original concept for the ZTK Interconnector was a high voltage 330 kV transmission line going from Pensulo (Zambia) to Nairobi (Kenya) with three connection points in Tanzania (Mbeya, Singida and Arusha). At that time, Tanzania grid was operated at 220 kV. The original concept of the ZTK Interconnector has been replaced, by two interconnections between two national grids: the Kenya-Tanzania Interconnection and the Zambia-Tanzania Interconnection.</p>

Capex Cost
162.00USD million
Preparation Cost
5.00
Operation Cost
3.24
Project Risk

<p>The major risks facing the interconnection project were identified and analysed.</p>
<p>Among these risks, special attention is warranted to the following categories of risks and to the measures to</p>
<p>mitigate them:</p>
<p>? Operational risks (in particular, the risks arising from organizational or technical reasons);</p>
<p>? Financial risks;</p>
<p>? Risks related to the environmental and social impacts;</p>
<p>While these risks and their impact are potentially serious, adequate mitigating measures, as indicated in</p>
<p>section 14, can reduce their likelihood of occurrence, diminish their impact, and ensure successful completion</p>
<p>and operation of the interconnection.</p>

Countries
Zambia, Kenya, Tanzania, Zambia, Kenya, Tanzania, Zambia
Beneficiary Countries
Kenya, Tanzania, Zambia
Stakeholders
African Union Development Agency
Common Market for Eastern and Southern Africa
Eastern Africa Power Pool
European Commission
Nile Equatorial Lakes Subsidiary Action Program
Southern African Development Community
Southern African Power Pool
World Bank
Zambia Electricity Supply Company
Zambia Office for the Promotion of Private Power Investment
Zambia - Ministry of Energy
European Commission
Start Date
Date Created Raw
Updated Date
Latitude
-11.150000
Longitude
31.547200
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.03.01
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of 122km / 400 kV section of the ZTK transmission interconnector from Mbeya (Tanzania) to Tunduma (border with Zambia).</p>
Description

<p>Construction of a transmission line that connects the power networks of Zambia, Tanzania and Kenya. This project includes the section of 400kV, 292km Iringa - Kisada - Mbeya transmission line,&Acirc; 122km of 400kV Mbeya - Tunduma transmission line and 4km of 400kV transmission line from Tunduma to Border of Zambia.&Acirc; </p>

Capex Cost
123.00USD million
Preparation Cost
24.00
Operation Cost
2.46
Project Risk

<ul>
<li>Environmental Risks: Minimal Social Risks: Minimal Socio-Enviro Classification: C - minimal social and environmental impacts Other External Risks: Not Reported</li>
</ul>

Countries
Tanzania, Kenya, Tanzania, Zambia, Kenya, Tanzania, Zambia
Beneficiary Countries
Kenya, Tanzania, Zambia
Stakeholders
East African Community
Tanzania Electricity Supply Company
Eastern Africa Power Pool
Southern African Development Community
African Union Development Agency
Common Market for Eastern and Southern Africa
Tanzania Ministry of Energy
World Bank
Agence Franaaise de Developement
Agence Franaaise de Developement
World Bank
Updated Date
Latitude
-8.910000
Longitude
33.460800
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.03.01
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of 414 km / 400 kV section of the ZTK transmission interconnector from Singida (Tanzania) to Namanga (border with Kenya).</p>
Description

<p>Construction of a transmission linethat connects the power networks ofTanzania and Kenya. This projectincludes the section of 414km of400kV transmission line from Singidato Namanga via Arusha. The designcapacity is 2,000MW.</p>

Capex Cost
242.00USD million
Preparation Cost
24.00
Operation Cost
127.00
Project Risk

<ul>
<li>Environmental Risks: Minimal Social Risks: Minimal Socio-Enviro Classification: C - minimal social and environmental impacts Other External Risks: Not Reported</li>
</ul>

Countries
Tanzania, Kenya, Tanzania, Zambia, Kenya, Tanzania, Zambia
Beneficiary Countries
Kenya, Tanzania, Zambia
Stakeholders
East African Community
Tanzania Electricity Supply Company
Eastern Africa Power Pool
Southern African Development Community
African Union Development Agency
Common Market for Eastern and Southern Africa
Tanzania Ministry of Energy
African Development Bank
Japanese International Cooperation Agency
African Development Bank
Japanese International Cooperation Agency
Start Date
Date Created Raw
Updated Date
Latitude
-2.550000
Longitude
36.784000
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.03.01
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of 670 km / 400 kV Iringa - Shinyanga section via Dodoma and Singida of the ZTK transmission interconnector on Tanzania side.</p>
Description

<p>Construction of a transmission line that connects the power networks of Zambia, Tanzania and Kenya. This project includes the section of 670km of 400kV transmission line from Iringa to Shinyanga via Dodoma and Singida.&Acirc; The&Acirc; design capacity of this section is 2000MW.</p>

Capex Cost
242.00USD million
Preparation Cost
24.00
Operation Cost
127.00
Project Risk

<ul>
<li>Environmental Risks: Minimal Social Risks: Minimal Socio-Enviro Classification: C - minimal social and environmental impacts Other External Risks: Not Reported</li>
</ul>

Countries
Tanzania, Kenya, Tanzania, Zambia, Kenya, Tanzania, Zambia
Beneficiary Countries
Kenya, Tanzania, Zambia
Stakeholders
East African Community
Tanzania Electricity Supply Company
Eastern Africa Power Pool
Southern African Development Community
African Union Development Agency
Common Market for Eastern and Southern Africa
Tanzania Ministry of Energy
World Bank
European Investment Bank
African Development Bank
Japanese International Cooperation Agency
Economic Development Cooperation Fund
African Development Bank
Economic Development Cooperation Fund
Japanese International Cooperation Agency
Email
ephrem.hailu@giz.de
Updated Date
Latitude
-6.370000
Longitude
34.888400
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.03.02
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of 96 km / 400 kV Kenya section of the ZTK transmission interconnector.</p>
Description

<p>Construction of a transmission line that connects the power networks of Zambia, Tanzania and Kenya. This project includes the section of 96km Kenyan section of the 2,800km ZTK interconnector&Acirc; from&Acirc; Arush in Tanzania to Isinya in Kenya. In Kenya, the line will be linked to the High Voltage Direct Current Interconnector between Kenya and Ethiopia.</p>

Capex Cost
50.00USD million
Preparation Cost
12.00
Operation Cost
0.00
Countries
Kenya, Kenya, Tanzania, Zambia, Kenya, Tanzania, Zambia, Lesotho
Beneficiary Countries
Kenya, Tanzania, Zambia
Stakeholders
African Union Development Agency
Common Market for Eastern and Southern Africa
East African Community
Eastern Africa Power Pool
Kenya Power and Lighting Company
Nile Equatorial Lakes Subsidiary Action Program
Start Date
Date Created Raw
Updated Date
Latitude
-1.290000
Longitude
36.819900
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.12.01
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>The project involved the construction of a 147 MW Ruzizi III hydro-electric dam and distribution station between Rwanda and the Democratic Republic of Congo, on the Ruzizi river.</p>
Description

<p>A 147&Acirc; MW hydropower plant will be constructred on the Ruzizi River. It will provide electricity supply to Rwanda, Burundi and the&Acirc; DRC.&Acirc; It entails the construction of a run-of-river dam between DRC and Rwanda, downstream from the Ruzizi II hydropower dam, a 147&Acirc; MW power plant and a distribution station. Power will be transmitted to the three countries from the Kamanyola substation by 220 kV transmission lines.</p>
<p>The Ruzizi III project will significantly transform the electricity sectors in the countries concerned. Its implementation will contribute to:&Acirc; </p>
<p>(i) optimal exploitation of the Ruzizi River's energy potential to improve security of supplies and access to electricity; and</p>
<p>(ii) the strengthening of regional economic integration by creating a market for electricity.</p>

Capex Cost
614.00USD million
Preparation Cost
11.20
Operation Cost
0.00
Countries
Burundi, Democratic Republic of Congo, Rwanda, Burundi, Democratic Republic of Congo, Rwanda, Burundi, Democratic Republic of Congo, Rwanda
Beneficiary Countries
Burundi, Democratic Republic of Congo, Rwanda
REC
EAC
Stakeholders
African Development Bank
East African Community
Eastern Africa Power Pool
Électricité des Grands Lacs
European Development Fund
European Investment Bank
KfW Development Bank
Rwanda Energy Group
World Bank
African Development Bank
European Development Fund
European Investment Bank
KfW Development Bank
World Bank
Email
egetahun@outlook.com
Start Date
Date Created Raw
Updated Date
Latitude
-1.940000
Longitude
30.087900
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Alternative Names
Masaka–Mutukula–Kyaka–Nyakanazi–MwanzaHigh Voltage Power Line (EastAfricannewspaper)
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
<p>Construction of a 98km at 220kVtransmission line from Masaka and Mwanza</p>
Description

<p>This is a 98km at 220kV, identified as one of the least cost transmission project during development of the 2009 Tanzania Power System Master Plan and the East African Community Power System Master Plan.</p>
<p> </p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Project Risk

<p>Not available</p>

Countries
Tanzania, Tanzania, Tanzania, Uganda
Beneficiary Countries
Tanzania
REC
EAC
Stakeholders
African Union Development Agency
Tanzania Electricity Supply Company
Tanzania Electricity Supply Company
East African Community
Eastern Africa Power Pool
Start Date
Date Created Raw
Updated Date
Latitude
-2.520000
Longitude
32.917400
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.01.01
Project Status
Active
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Alternative Names
Millennium Dam
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of the Grand Ethiopean Renaissance Dam (GERD) with a 6000 MW hydropower facility on the Blue Nile river in the Benshangul Gumuz region of Ethiopia.</p>
<p> </p>
Description

<p>The Grand Ethiopian Renaissance Dam (GERD ) formerly known as the Millennium Dam and sometimes referred to as Hidase Dam, is a gravity dam on the Blue Nile River in Ethiopia currently under construction. It is in the Benishangul-Gumuz Region of Ethiopia, about 40 km east of the border with Sudan. At 6,000 MW, the dam will be the largest hydroelectric power plant in Africa when completed, as well as the 8th largest in the world. The reservoir at 72&Acirc; billion cubic meters will be one of the continent's largest. According to the Ethiopian government, as of June&Acirc; &Acirc; 2017, the Dam is 60% complete.</p>
<p> </p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Project Risk

<ul>
<li>Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li>
</ul>

Countries
Ethiopia, Ethiopia, Egypt, Ethiopia, Sudan
Beneficiary Countries
Ethiopia
Stakeholders
Common Market for Eastern and Southern Africa
Eastern Africa Power Pool
Ethiopian Electricity Power Cooperation
Nile Basin Initiative
Inter-Governmental Authority on Development (IGAD)
Email
egetahun@outlook.com
Start Date
Date Created Raw
Updated Date
Latitude
11.220000
Longitude
35.093800
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.02.01
Project Status
Stall
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Alternative Names
GERD-Rabak
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Construction of the Ethiopia section of the 580km / 500 kV Ethiopia to Sudan transmission interconnector. The project comprises a power transmission interconnector between Ethiopia and Sudan, including 580km of new 500kV transmission lines, of which approximately 16km will be in Ethiopia, starting at the Grand Ethiopia Renaissance Dam (GERD).</p>
<p> </p>
Description

<p>Construction of a transmission line (580 km / 500 kV) that connects the power networks of Ethiopia and Sudan to facilitate trading in electricity and promote power systems stability. The interconnector will have a transmission capacity of 3000 MW.</p>
<p>The Project also includes two new, 500kV capacitated substations at Rabak and Jebel Aulia (both in Sudan), and power line bay&Acirc; extensions at the following existing substations: Grand Renaissance (500kV Ethiopia), Rabak&Acirc; (220kV, Sudan) and Jebel Aulia (220kV, Sudan).&Acirc; </p>
<p>Construction of a 500kV transmission line and the associated substations that connects the power networks of Ethiopia and Sudan to facilitate trading in electricity and promote power systems stability. The line will be 580 km in total, 564 km in Sudan, terminating in Khartoum, 16 km in Ethiopia, terminating at the Grand Renaissance Dam. The Project also includes two new, 500 kV capacitated substations at Rabak and Jebel Aulia (both in Sudan), and power line bay extensions at the following existing substations: Grand Renaissance (500kV Ethiopia), Rabak (220kV, Sudan) and Jebel Aulia (220kV, Sudan).</p>
<p>It is expected that the project would assist the two partners to obtain the following specific benefits: to promote power system stability in the countries concerned; to promote energy connectivity among the countries by assisting them to integrate their respective networks and thereby develop ability for building larger power projects to meet larger regional markets; to develop ability to negotiate better terms for procurement of power equipment and technical assistance; to reduce the cost of power in both countries; in the long term, complete integration of the power systems in Egypt and Sudan; and to create productive employment and economic development across the borders. The main objectives of the project include provision of transmission capacity to cater for grid interconnection between Egypt and Sudan, provision of transmission infrastructure to cater for future grid interconnections to other countries, promotion of regional cooperation through sharing of power generation resources and facilitation of rural electrification and improve the standard of living for the population in project areas</p>
<p> </p>
<p> </p>
<p> </p>

Capex Cost
29,030,000.00USD million
Preparation Cost
186.00
Operation Cost
290,300.00
Project Risk

<ul>
<li>Environmental Risk: Potential impact during the construction and operational phases relating to biodiversity and ecosystems (including avifauna), material use as it impacts on soil and groundwater recharge as well as solid waste and wastewater pollution impact on water bodies</li>
<li>Socio-economic Risk: Potential impact during the construction and operational phases relating to quality of air and dust emissions, noise and other nuisance as well as the impact on tourism and cultural heritage due to visual and aesthetic impacts. Resettlement necessary for project-affected communities. Furthermore, possible adverse community health and safety effects from electromagnetic fields.</li>
<li>Construction Risk: A comprehensive set of risks have been identified, including potential degradation and damage of the existing structures including any archaeological materials and terrain due to excavation,</li>
<li>Operation Risk: Collision of birds with conductors, permanent interference between the project and local habitats as well as air emissions from maintenance equipment.</li>
</ul>
<p>The Feasibility Study highlights two sets of project-related risks in the ESMP, namely construction risk and operation risk. - adverse physical and/or economic impacts, temporary or permanent displacement, as well as temporary or permanent loss of assets, facilities or access to resource such as crops, woodlots, grazing lands, wells, businesses and services, etc. Among the risks identified, the Project considered the social risk of resettlement as being particularly serious</p>
<p> </p>

Countries
Ethiopia, Ethiopia, Sudan, Ethiopia, Sudan
Beneficiary Countries
Ethiopia, Sudan
Stakeholders
Common Market for Eastern and Southern Africa
Eastern Africa Power Pool
Ethiopia - Government of Ethiopia
Ethiopian Electricity Power Cooperation
Ethiopian Minister of Water
Irrigation and Electricity
Nile Basin Initiative
Sudan - Government of Sudan
Inter-Governmental Authority on Development (IGAD)
Eastern Nile Technical Regional Office - ENTRO
Start Date
Date Created Raw
Updated Date
Latitude
15.600000
Longitude
32.535600
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.02.02.02
Project Status
Stall
Project Stage
Feasibility
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
<p>Implementation of Sudan section of the 500 kV Ethiopia to Sudan transmission interconnection line and the associated high voltage substations based on the conclusions of the final feasibility. The Project comprises a power transmission interconnector between Ethiopia and Sudan, including 580km of new 500kV transmission lines, of which approximately 564km will be in Sudan, terminating in Khartoum.</p>
Description

<p> Construction of a 500 kV transmission line and the associated substations that connects the power networks of Ethiopia and Sudan to facilitate trading in electricity and promote power systems stability. The Project also includes two new, 500 kV capacitated substations at Rabak and Jebel Aulia (both in Sudan), and power line bay extensions at the following existing substations: Grand Renaissance (500kV Ethiopia), Rabak (220kV, Sudan) and Jebel Aulia (220kV, Sudan).</p>
<p> </p>

Capex Cost
484,940.00USD million
Preparation Cost
186.00
Operation Cost
29.03
Project Risk

<ul>
<li>Environmental Risk: Potential impact during the construction and operational phases relating to biodiversity and ecosystems (including avifauna), material use as it impacts on soil and groundwater recharge as well as solid waste and wastewater pollution impact on water bodies</li>
<li>Socio-economic Risk: Potential impact during the construction and operational phases relating to quality of air and dust emissions, noise and other nuisance as well as the impact on tourism and cultural heritage due to visual and aesthetic impacts. Resettlement necessary for project-affected communities. Furthermore, possible adverse community health and safety effects from electromagnetic fields.</li>
<li>Construction Risk: A comprehensive set of risks have been identified, including potential degradation and damage of the existing structures including any archaeological materials and terrain due to excavation,</li>
<li>Operation Risk: Collision of birds with conductors, permanent interference between the project and local habitats as well as air emissions from maintenance equipment.</li>
</ul>
<p>The Feasibility Study highlights two sets of project-related risks in the ESMP, namely construction risk and operation risk. - adverse physical and/or economic impacts, temporary or permanent displacement, as well as temporary or permanent loss of assets, facilities or access to resource such as crops, woodlots, grazing lands, wells, businesses and services, etc. Among the risks identified, the Project considered the social risk of resettlement as being particularly serious</p>
<p> </p>

Countries
Sudan, Ethiopia, Sudan, Ethiopia, Sudan
Beneficiary Countries
Ethiopia, Sudan
Stakeholders
Common Market for Eastern and Southern Africa
Eastern Africa Power Pool
Ethiopia - Government of Ethiopia
Nile Basin Initiative
Sudan - Government of Sudan
Sudan Ministry of Water Resources
Irrigation and Electricity
Inter-Governmental Authority on Development (IGAD)
Eastern Nile Technical Regional Office - ENTRO
Start Date
Date Created Raw
Updated Date
Latitude
15.500000
Longitude
32.555700