Lake Chad Basin Commission

By Anonymous (not verified) , 24 February 2026
PIDA Code
W.01.01
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Water
Subsector Name
Multi-purpose Reservoir
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of an Oubangui flow control dam to allow river navigation between Bangui and Congo and the Democratic Republic of Congo (DRC); in the Congo River Basin, and electricity production to supply Bangui and surrounding areas in the DRC and Congo.
Improve the navigability of Obangui River with an added hydropower component.
Description

<p>The project aims to provide solutions to the problems of interruption of navigation on Oubangui River, tributary of the Congo River in the region of Central Africa. This is particularly the case during periods of low water levels, and the supply of electricity to the Central African Republic (CAR), North Congo and the Congo. DRC, through the construction of a Oubangui flow control and power generation dam at the Palambo site, is about 60 km upstream from Bangui.</p>

<p>The characteristics of the scenario chosen among the solutions proposed by SOGREAH in 1990 were as follows:</p>

<ul>
<li>Normal retention rating of 361 m;</li>
<li>Height of the dam of approximately 18 m;</li>
<li>Area of 606 x106 m 2;</li>
<li>Length of approximately 1,200 m;</li>
<li>Minimum downstream flow to reach at Zinga, about 70 km downstream from Bangui of 920 m3 / s;</li>
<li>Storage volume of 2,370 million m3;</li>
<li>Power generation of 30 MW;</li>
<li>Number of groups of 4 bulbs (unit flow: 94 m3 / s).</li>
</ul>

Capex Cost
0.00USD million
Preparation Cost
3.00
Operation Cost
0.00
Project Risk

Mobilization of finances to carry out the studies of: Summary preliminary project (APS), Final preliminary project (APD), Tender dossier (DAO)

Countries
Central African Republic, Democratic Republic of Congo, Central African Republic, Democratic Republic of Congo, Central African Republic, Democratic Republic of Congo
Beneficiary Countries
Central African Republic, Democratic Republic of Congo
REC
CEEAC-ECCAS
Stakeholders
Central African Economic and Monetary Community
Economic Community of Central African States
Global Water Partnership
Lake Chad Basin Commission
Zambia - Ministry of Water Development
Sanitation and Environmental Protection
Email
christine.razanamahandry@gmail.com
Start Date
Date Created Raw
Updated Date
Latitude
4.660000
Longitude
18.918100
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Project Definition
Completion Percentage
0
Sector Name
ICT
Alternative Names
Not available
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
<p>The project envisages the implementation of six Data Centers in Burundi, Central African Republic, Sao Tome, Chad, Equatorial Guinea, Gabon- and the reinforcement of five &ndash;Angola, Republic of Congo, Cameroun, Rwanda, Democratic Republic of Congo.</p>
<pre id="tw-target-text" class="tw-data-text tw-text-large tw-ta" dir="ltr" style="font-size: 28px; line-height: 36px; background-color: #f8f9fa; border: none; padding: 2px 0.14em 2px 0px; position: relative; margin-top: -2px; margin-bottom: -2px; resize: none; font-family: inherit; overflow: hidden; width: 270px; text-wrap: wrap; overflow-wrap: break-word; color: #1f1f1f;" data-placeholder="Translation" aria-label="Translated text" data-ved="2ahUKEwiOz5G44fGHAxWKUEEAHU1CHnkQ3ewLegQIBxAU"><span class="Y2IQFc" lang="en" style="font-size: 12pt;">This project aims to provide the ECCAS subregional space with
infrastructures which participate in the securing cyberspace and help create trust in a world increasingly
digital and to guarantee the
digital sovereignty of States.</span></pre>
Description

<p>The project envisages the implementation of six Data Centers in Burundi, Central African Republic, Sao Tome, Chad, Equatorial Guinea, Gabon- and the reinforcement of five &ndash;Angola, Republic of Congo, Cameroun, Rwanda, Democratic Republic of Congo.</p>
<pre id="tw-target-text" class="tw-data-text tw-text-large tw-ta" dir="ltr" style="font-size: 28px; line-height: 36px; background-color: #f8f9fa; border: none; padding: 2px 0.14em 2px 0px; position: relative; margin-top: -2px; margin-bottom: -2px; resize: none; font-family: inherit; overflow: hidden; width: 270px; text-wrap: wrap; overflow-wrap: break-word; color: #1f1f1f;" data-placeholder="Translation" aria-label="Translated text" data-ved="2ahUKEwiOz5G44fGHAxWKUEEAHU1CHnkQ3ewLegQIBxAU"><span class="Y2IQFc" lang="en"><span style="font-size: 12pt;">This project aims to provide the ECCAS subregional space with
infrastructures which participate in the securing cyberspace and
help create trust in a world increasingly digital and to guarantee the digital sovereignty of States.</span></span></pre>
<p> </p>

Capex Cost
0.00USD million
Preparation Cost
92,500,000.00
Operation Cost
0.00
Project Risk

<p>Not available</p>

Countries
Burundi, Central African Republic, Sao Tome and Principe, Chad, Equatorial Guinea, Angola, Democratic Republic of Congo, Cameroon, Rwanda
Beneficiary Countries
Angola, Democratic Republic of Congo, Cameroon, Rwanda
REC
CEEAC-ECCAS
Stakeholders
Angola - Government of Angola
Burundi - Government of Burundi
Gabon - Ministère de l’Équipement
des Infrastructures et de l’Aménagement du Territoire
Ethiopian Revenues and Customs Authority
Autoridade Geral de Regulação
Cameroon Telecommunication
Economic Community of Central African States
Lake Chad Basin Commission
Rwanda - Government of Rwanda
Start Date
Date Created Raw
Latitude
0.400000
Longitude
9.445060