Central Corridor Transit Transport Facilitation Agency

Acronym
CCTTFA
Remote ID
258
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.02.01
Project Status
Completed
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Border Post
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of Rusumo One-Stop Border Post between Tanzania and Rwanda, which lies on the Central Corridor.
Description

<p>Construction of Rusumo One-Stop Border Post between Tanzania and Rwanda, which lies on the Central Corridor. Border type: Juxtaposed and on the borderline of the Kagera River. </p>

<p>The facility on the Rwandan side was completed and handed over (to DGIE) in December<br>
2015 and handover of the facility on the Tanzanian side (to TRA) in October 2015. </p>

Capex Cost
0.00USD million
Preparation Cost
37.20
Operation Cost
0.00
Countries
Rwanda, Tanzania, Rwanda, Tanzania, Rwanda, Tanzania
Beneficiary Countries
Rwanda, Tanzania
REC
EAC
Stakeholders
Central Corridor Transit Transport Facilitation Agency
East African Community
Japanese International Cooperation Agency
Rwanda Revenue Authority
Tanzania Revenue Authority
TradeMark East Africa
United States Agency for International Development
Email
ephrem.hailu@giz.de
Start Date
Date Created Raw
Updated Date
Latitude
-2.380000
Longitude
30.783700
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.02
Project Status
Active
Project Stage
Construction
Completion Percentage
1
Sector Name
Transport
Subsector Name
Road
Alternative Names
Multinational Nyakanazi-Kidawe/Kasulu-Manyovu (Tanzania)-Rumonge-Rutunga-Bujumbura (Burundi) road section
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The road is very important for trade, transport and tourism for the East African region. It is located along the Lake Tanganyika. The road is an alternative way toward Dar Es Salaam Port through Kasulu or Kigoma. The works planned are rehabilitation and widening from 6m to 7m. By upgrading of this road, it will be easier for users to reach Kigoma and Dar Es Salaam(TZ), Rumonge and Bujumbura (BDI), Uvira and Goma (DRC), Cyangugu and Gisenyi (RW). Some sections have been updated, studies are going on for others.
Description

<p>Upgrading of the Bujumbura-Rumonge-Nyanza Lac-Mugina (RN3) road will improve trade, transport and tourism in the East African region. The road is described as </p>

<p> </p>

<p>1) Rumonge-Nyanza Lac (45 km): Works are planned, funds from BADEA;</p>

<p> </p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Burundi, Burundi, Burundi
Beneficiary Countries
Burundi
REC
EAC
Stakeholders
Central Corridor Transit Transport Facilitation Agency
DRC - Le bureau des Routes
Burundi Ministry of Transport
Public Works and Equipment
East African Community
Arab Bank for economic development in Africa
Email
ephrem.hailu@giz.de
Updated Date
Latitude
-4.340000
Longitude
29.602700
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.02
Project Status
Active
Project Stage
Construction
Completion Percentage
1
Sector Name
Transport
Subsector Name
Road
Alternative Names
Multinational Nyakanazi-Kidawe/Kasulu-Manyovu (Tanzania)-Rumonge-Rutunga-Bujumbura (Burundi) road section
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The road is very important for trade, transport and tourism for the East African region. It is located along the Lake Tanganyika. The road is an alternative way toward Dar Es Salaam Port through Kasulu or Kigoma. The works planned are rehabilitation and widening from 6m to 7m. By upgrading of this road, it will be easier for users to reach Kigoma and Dar Es Salaam(TZ), Rumonge and Bujumbura (BDI), Uvira and Goma (DRC), Cyangugu and Gisenyi (RW). Some sections have been updated, studies are going on for others.
Description

<p>Upgrading of the Bujumbura-Rumonge-Nyanza Lac-Mugina (RN3) road will improve trade, transport and tourism in the East African region. The road has 3 main sections:</p>

<p>1) Bujumbura-Rumonge (78 km): Studies of its upgrading are ongoing, NEPAD/IPPF funds;</p>

<p>2) Rumonge-Nyanza Lac (45 km): Works are planned, funds from AfDB;</p>

<p>3) Nyanza Lac-Mugina (45 km): Upgrading completed.</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Burundi, Burundi, Burundi
Beneficiary Countries
Burundi
REC
EAC
Stakeholders
Central Corridor Transit Transport Facilitation Agency
DRC - Le bureau des Routes
Burundi Ministry of Transport
Public Works and Equipment
East African Community
Email
ephrem.hailu@giz.de
Updated Date
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.01
Project Status
Active
Project Stage
Construction
Completion Percentage
1
Sector Name
Transport
Subsector Name
Road
Alternative Names
Lot1: Nyakararo-Mwaro-Kibumbu (26 km)
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The national road 18: Nyakararo-Mwaro-Gitega (56 km) is a missing link of the Central Corridor Bujumbura-Mwaro-Gitega-Kobero (Burundi)/Kabanga-Dodoma-Dar Es Salaam (Tanzania).
Until 2015, the road was still in gravel. From 2016, it is being upgraded and widened from 6m to 7m. The first lot: Nyakararo-Mwaro-Kibumbu (26 km) is completed. The remaining lot: Kibumbu-Mweya-Gitega will also be upgraded with AfDB funds.
Description

<p>RN18 is a 56km road on the Central Corridor along the RN7- RN18- RN16 route and is a conduit for movement of traffic from Tanzania to Gitega and Bujumbura. RN18 requires upgrading from gravel to asphalt concrete and expansion of the carriageway from 6 metres to 7 metres.</p>

Capex Cost
50.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Burundi, Burundi, Burundi
Beneficiary Countries
Burundi
REC
EAC
Stakeholders
Central Corridor Transit Transport Facilitation Agency
DRC - Le bureau des Routes
Burundi Ministry of Transport
Public Works and Equipment
East African Community
Email
ephrem.hailu@giz.de
Updated Date
Latitude
-3.480000
Longitude
29.776400
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.02
Project Status
Active
Project Stage
Construction
Completion Percentage
1
Sector Name
Transport
Subsector Name
Road
Alternative Names
Multinational Nyakanazi-Kidawe/Kasulu-Manyovu (Tanzania)-Rumonge-Rutunga-Bujumbura (Burundi) road section
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The road is very important for trade, transport and tourism for the East African region. It is located along the Lake Tanganyika. The road is an alternative way toward Dar Es Salaam Port through Kasulu or Kigoma. The works planned are rehabilitation and widening from 6m to 7m. By upgrading of this road, it will be easier for users to reach Kigoma and Dar Es Salaam(TZ), Rumonge and Bujumbura (BDI), Uvira and Goma (DRC), Cyangugu and Gisenyi (RW). Some sections have been updated, studies are going on for others.
Description

<p>Upgrading of the Bujumbura-Rumonge-Nyanza Lac-Mugina (RN3) road will improve trade, transport and tourism in the East African region. The road has 3 main sections:</p>

<p>1) Bujumbura-Rumonge (78 km): Studies of its upgrading are ongoing, NEPAD/IPPF funds;</p>

<p>2) Rumonge-Nyanza Lac (45 km): Works are planned, funds from AfDB;</p>

<p>3) Nyanza Lac-Mugina (45 km): Upgrading completed.</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Burundi, Burundi, Burundi
Beneficiary Countries
Burundi
REC
EAC
Stakeholders
Central Corridor Transit Transport Facilitation Agency
DRC - Le bureau des Routes
Burundi Ministry of Transport
Public Works and Equipment
East African Community
Arab Bank for economic development in Africa
Email
ephrem.hailu@giz.de
Updated Date
Latitude
-3.890000
Longitude
29.549100
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.02
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Alternative Names
Multinational Nyakanazi-Kidawe/Kasulu-Manyovu (Tanzania)-Rumonge-Rutunga-Bujumbura (Burundi) road section
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The road is very important for trade, transport and tourism for the East African region. It is located along the Lake Tanganyika. The road is an alternative way toward Dar Es Salaam Port through Kasulu or Kigoma. The works planned are rehabilitation and widening from 6m to 7m. By upgrading of this road, it will be easier for users to reach Kigoma and Dar Es Salaam(TZ), Rumonge and Bujumbura (BDI), Uvira and Goma (DRC), Cyangugu and Gisenyi (RW). Some sections have been updated, studies are going on for others.
Description

<p>Upgrading of the Bujumbura-Rumonge-Nyanza Lac-Mugina (RN3) road will improve trade, transport and tourism in the East African region. The road has 3 main sections:</p>

<p>1) Bujumbura-Rumonge (78 km): Studies of its upgrading are ongoing, NEPAD/IPPF funds;</p>

<p>2) Rumonge-Nyanza Lac (45 km): Works are planned, funds from AfDB;</p>

<p>3) Nyanza Lac-Mugina (45 km): Upgrading completed.</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Burundi, Burundi, Burundi
Beneficiary Countries
Burundi
REC
EAC
Stakeholders
Central Corridor Transit Transport Facilitation Agency
DRC - Le bureau des Routes
Burundi Ministry of Transport
Public Works and Equipment
East African Community
Email
ephrem.hailu@giz.de
Updated Date
Latitude
-3.360000
Longitude
29.359900