Zambia Road Development Agency

Acronym
RDA
Remote ID
442
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.06.03.01.03
Project Status
Active
Project Stage
Construction
Completion Percentage
1
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of Link 3 of the Serenje - Nakonde Road between Chinsali and Nakonde in Zambia (208.6 km).
Description

<p>The Serenje-Nakonde project road runs in a north eastern direction from Serenje in Zambia&#39;s Central Province to Nakonde (at the border post between Zambia and Tanzania) in the Northern Province covering a total distance of 611.5 km. The road is divided in 3 links: Link 1: Serenje to Mpika (238.3 km), Link 2: Mpika to Chinsali (164.6 k), Link 3: Chinsali to Nakonde (208.6 km) The Serenje-Nakonde road is part of the Regional Trunk Road Network (RTRN Link 15) as well as the Trans-African Highway Nr 4.</p>

Capex Cost
169.00USD million
Preparation Cost
1.18
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li></ul>

Countries
Zambia, Zambia, Botswana, Democratic Republic of Congo, Malawi, Namibia, Tanzania, Zambia, Zimbabwe
Beneficiary Countries
Zambia
REC
COMESA
Stakeholders
Zambia Road Development Agency
UK Department for International Development
Common Market for Eastern and Southern Africa
European Development Fund
African Development Bank
South Africa - Transnet
Zambia - Ministry of Housing and Infrastructure Development
Zambia - Ministry of Transport and Communications
European Development Fund
Email
ephrem.hailu@giz.de
Start Date
Date Created Raw
Updated Date
Latitude
-9.990000
Longitude
32.450700
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.06.03.01.02
Project Status
Active
Project Stage
Construction
Completion Percentage
1
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of Link 2 of the Serenje - Nakonde Road Link between Mpika and Chinsali in Zambia (164.6 km).
Description

<p>The Serenje-Nakonde project road runs in a north eastern direction from Serenje in Zambia&#39;s Central Province to Nakonde (at the border post between Zambia and Tanzania) in the Northern Province covering a total distance of 611.5 km. The road is divided in 3 links: Link 1: Serenje to Mpika (238.3 km), Link 2: Mpika to Chinsali (164.6m), Link 3: Chinsali to Nakonde (208.6 km) The Serenje-Nakonde road is part of the Regional Trunk Road Network (RTRN Link 15) as well as the Trans-African Highway Nr 4.</p>

Capex Cost
142.00USD million
Preparation Cost
1.24
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li></ul>

Countries
Zambia, Zambia, Botswana, Democratic Republic of Congo, Malawi, Namibia, Tanzania, Zambia, Zimbabwe
Beneficiary Countries
Zambia
REC
COMESA
Stakeholders
Zambia Road Development Agency
UK Department for International Development
Common Market for Eastern and Southern Africa
European Development Fund
South Africa - Transnet
Zambia - Ministry of Housing and Infrastructure Development
Zambia - Ministry of Transport and Communications
European Development Fund
Email
ephrem.hailu@giz.de
Start Date
Date Created Raw
Updated Date
Latitude
-11.250000
Longitude
31.789000
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.06.03.01.01
Project Status
Active
Project Stage
Construction
Completion Percentage
1
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading Link 1 (from Serenje to Mpika) of the Serenje - Nakonde Road in Zambia (238.3 km).
Description

<p>The Serenje-Nakonde project road runs in a north eastern direction from Serenje in Zambia&#39;s Central Province to Nakonde (at the border post between Zambia and Tanzania) in the Northern Province covering a total distance of 611.5 km. The road is divided in 3 links: Link 1: Serenje to Mpika (238.3 km), Link 2: Mpika to Chinsali (164.6 k), Link 3: Chinsali to Nakonde (208.6 km) The Serenje-Nakonde road is part of the Regional Trunk Road Network (RTRN Link 15) as well as the Trans-African Highway Nr 4.</p>

Capex Cost
202.00USD million
Preparation Cost
0.87
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li></ul>

Countries
Zambia, Zambia, Botswana, Malawi, Namibia, Republic of Congo, Tanzania, Zambia, Zimbabwe
Beneficiary Countries
Zambia
REC
COMESA
Stakeholders
Zambia Road Development Agency
UK Department for International Development
Common Market for Eastern and Southern Africa
European Development Fund
South Africa - Transnet
Zambia - Ministry of Housing and Infrastructure Development
Zambia - Ministry of Transport and Communications
European Development Fund
Email
ephrem.hailu@giz.de
Start Date
Date Created Raw
Updated Date
Latitude
-12.560000
Longitude
30.845600