Construction of the Koloko/Heremakono OSBP between Mali and Burkina Faso. Koloko lies on the Burkina Faso side, while Heremakono is located on the side of Mali. The OSBP lies on the Dakar- Bamako- Niamey Corridor.
Description
<p>Construction of the Koloko/Heremankono OSBP between Mali and Burkina Faso on the Dakar-Bamako-Niamey transport corridor.</p>
Capex Cost
13.60USD million
Preparation Cost
0.03
Operation Cost
0.00
Project Risk
<ul><li>Social Risks: Health risks due to workers staying in community. Socio-Environmental Classification: B - limited and/or reversible social and economic impacts </li></ul>
Countries
Burkina Faso, Mali, Burkina Faso, Mali, Burkina Faso, Mali
Construction of Hillacondji/Sanveekondji One-Stop Border Post between Togo and Benin, with Hillacondji on the Benin side and Sanveekondji on the side of Togo. The OSBP lies on the Abidjan- Lagos Corridor.
Description
<p>Construction of Hillacondji/Sanveekondji One-Stop Border Post between Togo and Benin. This is a Joint Border Control Facility for border control officials from Benin and Togo to jointly undertake border control formalities to reduce border crosing time for goods and persons. OSBT: Straddling.</p>
Capex Cost
14.00USD million
Preparation Cost
3.00
Operation Cost
0.00
Project Risk
<ul><li> Socio-Environmental Classification: C - minimal social and environmental impacts </li></ul>
Countries
Benin, Togo, Benin, Togo, Benin, Togo
Beneficiary Countries
Benin, Togo
REC
ECOWAS-CEDEAO
Stakeholders
Economic Community of West African States
Benin - Direction Générale des Impôts et des Domaines
Construction of Elubo/ Noe One-Stop Border Post between Cote d'Ivoire and Ghana. Elubo lies on the Ghananian side while Noe on side of Cote d'Ivoire and the border is situated on the Abidjan-Lagos Corridor.
Description
<p>Construction of Elubo/Noe One-Stop Border Post (Cote d'Ivoire and Ghana). The OSBP lies on the Abidjan-Lagos Corridor. OSBP type: juxtaposed.</p>
Construction of a 225 kV, double circuit steel lattice tower overhead transmission line of appromiximately 1,304 km, 10 new Substations (4 in Liberia, 5 in Sierra Leone, 1 in Guinea and extension of the 225 kV Man Substation in CA´te d"™Ivoire), installation of Static Var Compensators at five substations, development of WAPP Control Area Centre in Guinea and the extension of the national Control Centre in CA´te d"™Ivoire for supervision of the transmission line, setting up of a Regional SCADA System and frequency control systems.
Description
This project forms part of the priority projects identified in the ECOWAS Master Plan for the Generation and Transmission of Electrical Energy and shall interconnect Sierra Leone, Liberia and Guinea to the nine already interconnected countries.
Capex Cost
549.30USD million
Preparation Cost
11.46
Operation Cost
0.00
Project Risk
Delay in the project implementation
Delay in payment of compensation to project affected persons
Countries
Côte d'Ivoire, Guinea, Liberia, Sierra Leone, Côte d'Ivoire, Guinea, Liberia, Sierra Leone
REC
ECOWAS-CEDEAO
Stakeholders
West Africa Power Pool
CLSG Regional Transmission Company
Côte d'Ivoire - Société des Énergies de Côte d'Ivoire
Guinea - La Société Électricité de Guinée
Sierra Leone - Electricity Distribution and Supply Authority