Active

Remote ID
1
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.09.03.01
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Reinforcement of the Egypt part of the 340 km / 500 kV Egypt to Libya section of the ELTAM transmission interconnector.
Description

This project forms part of the ELTAM transmission interconnector which connects the power markets of Egypt, Libya, Tunisia, Algeria and Mali. In particular, it involves the reinforcement of the Egypt part of the 340 km / 500 kV Egypt to Libya section from the Mersa Matruh to the Libya border.

Capex Cost
250.00USD million
Preparation Cost
27.00
Project Risk

<ul><li> Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li></ul>

Countries
Egypt, Egypt, Libya, Egypt, Libya
Beneficiary Countries
Egypt, Libya
REC
UMA-AMU
Stakeholders
Arab Maghreb Union
Libya - General Electricity Company of Libya
Comité Maghrébin de l'Électricité
Email
ephremg@nepad.org
Updated Date
Latitude
31.470000
Longitude
26.157600
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.04.02
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Design and implement efficiency monitoring system
Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Stakeholders
African Union Commission
Email
egetahun@outlook.com
Start Date
Date Created Raw
Updated Date
Latitude
0.000000
Longitude
0.000000
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Project Definition
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
TBD
Description

<span [removed]: normal; font-variant-ligatures: normal; font-variant-caps: normal; font-weight: 500; letter-spacing: normal; orphans: 2; text-align: left; text-indent: 0px; text-transform: none; white-space: normal; widows: 2; word-spacing: 0px; -webkit-text-stroke-width: 0px; background-color: rgb(255, 255, 255); text-decoration-thickness: initial; text-decoration-style: initial; text-decoration-color: initial; display: inline !important; float: none;">The Guba (Ethiopia)-Khartoum project is one of the proposed cross boarder interconnection lines between five countries in the horn of Africa under the them 'Eastern Africa Green Power Transmission Network Project'. The countries involved include-Ethiopia,Djibouti Eritrea, Sudan, South Sudan, and Somalia. This will form a large regional transmission network which would be part of the Eastern African Power Pool. The project enables the countries in context to be supplied with green power at a reasonable price.</span><br>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Ethiopia, Sudan, Ethiopia, Sudan, Burundi, Democratic Republic of Congo, Egypt, Kenya, Rwanda, Tanzania, Uganda
Beneficiary Countries
Ethiopia, Sudan
Stakeholders
African Union Development Agency
Email
nguena.kitio1996@gmail.com
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.11.07
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Port
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Expansion of Durban Port (South Africa)
Description

<p>The port expansion for Durban are driven by the major container expansions required to ensure that the port component of the Durban to Gauteng Freight Corridor can meet future demand. Short term expansions will be made within the existing port followed by medium term development of a complementary new port on the old airport site, followed by a long term expansion in Bayhead.</p>

Capex Cost
2,910.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li></ul>

Countries
South Africa, South Africa, South Africa
Beneficiary Countries
South Africa
REC
SADC
Stakeholders
Southern African Development Community
South Africa - Transnet
Email
ephremg@nepad.org
Updated Date
Latitude
-29.860000
Longitude
31.036200
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.23
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of road from DSM to Manyoni to Isaka (Tanzania).
Description

<p>Upgrading of road from DSM to Manyoni to Isaka (Tanzania).</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Tanzania, Tanzania, Tanzania
Beneficiary Countries
Tanzania
REC
EAC
Stakeholders
East African Community
Tanzania National Roads Agency
Central Corridor Transit Transport Facilitation Agency
Email
ephremg@nepad.org
Updated Date
Latitude
0.000000
Longitude
0.000000
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.06.01.01
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The project aims to provide a direct transmission link between Angola and DRC, through the construction of the DRC section of the 260 km / 400 kV DRC line to Angola of the Inga-Cabinda-Pointe-Noire transmission interconnector.
Description

<p>The project is part of the Inga-Cabinda-Pointe Noire transmission interconnector, linking the power systems of DRC, Angola and Congo, with a transfer capacity of 600 MW. The project involves the construction of a section in DRC from Inga to the border with Angola.</p>

Capex Cost
191.00USD million
Preparation Cost
1.60
Operation Cost
0.00
Countries
Democratic Republic of Congo, Angola, Democratic Republic of Congo, Angola, Democratic Republic of Congo
Beneficiary Countries
Angola, Democratic Republic of Congo
REC
SADC
Stakeholders
Southern African Development Community
DRC - Société Nationale d'Électricité
Central Africa Power Pool
DRC - Ministry of Energy and Water Resources
Email
ephrem.hailu@giz.de
Start Date
Date Created Raw
Updated Date
Latitude
-5.480000
Longitude
13.065300
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.06.01.02
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
The project aims to provide a direct transmission link between Angola and DRC, through the construction of the Angola section of the 260 km / 400 kV DRC line from DRC of the Inga-Cabinda-Pointe-Noire transmission interconnector.
Description

<p>O projecto faz parte da interligação de transmissão Inga-Cabinda-Pointe Noire, ligando os sistemas de energia da RDC, Angola e Congo, com uma capacidade de transferência de 600 MW. <font [removed]="" inherit;"="">O projecto envolve a construção de uma secção em Angola desde a fronteira da RDC até Cabinda.</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Angola, Angola, Democratic Republic of Congo, Angola, Democratic Republic of Congo
Beneficiary Countries
Angola, Democratic Republic of Congo
REC
SADC
Stakeholders
Southern African Development Community
Angola - Empresa Nacional de Electricidade de Angola
Central Africa Power Pool
Angola - Rede Nacionale de Transporte de Electricidade
Email
ephrem.hailu@giz.de
Start Date
Date Created Raw
Updated Date
Latitude
-5.260000
Longitude
12.288200
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.21.03.01
Project Status
Active
Project Stage
Project Definition
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
*** DISCLAIMER: Project information was not obtained. It will be inserted when project information becomes available. *** Upgrading of Gabon section of the 236 km road from Doussala to Dolissie (Gabon).
Countries
Gabon, Gabon, Republic of Congo, Gabon, Republic of Congo
Beneficiary Countries
Gabon, Republic of Congo
REC
CEEAC-ECCAS
Stakeholders
Economic Community of Central African States
Gabon - Ministère de l’Équipement
des Infrastructures et de l’Aménagement du Territoire
Email
ephremg@nepad.org
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.21.03.02
Project Status
Active
Project Stage
Project Definition
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
*** DISCLAIMER: Project information was not obtained. It will be inserted when project information becomes available. *** Upgrading of Congo section of the 236 km road from Doussala to Dolissie (Congo).
Countries
Republic of Congo, Gabon, Republic of Congo, Gabon, Republic of Congo
Beneficiary Countries
Gabon, Republic of Congo
REC
CEEAC-ECCAS
Stakeholders
Economic Community of Central African States
Email
ephremg@nepad.org
By Anonymous (not verified) , 24 February 2026
Project Status
Active
Project Stage
Project Definition
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
<p>The doubling of the RN06 highway between</p>
<p>city of Mascara, with its high agricultural</p>
<p>and the southern town of Bechar</p>
<p>as well as the RN50 between Bechar and</p>
<p>city of Tindouf to continue</p>
<p>to the border with</p>
<p>Mauritania. This motorway axis can be</p>
<p>extended to the town of Choum in</p>
<p>Mauritania</p>
Description

<p>The RN06 crosses 06 wilayas for a total</p>
<p>total length of 2200 km. It starts</p>
<p>Mascara and ends at Timiaouine</p>
<p>Timiaouine (Malian border) The</p>
<p>RN50 begins at the level of the</p>
<p>RN 06 (B&eacute;char) crosses the territory</p>
<p>Bechar-Tindouf and Adrar on a linear</p>
<p>of 1252 km</p>

Capex Cost
0.00USD million
Preparation Cost
300.00
Countries
Algeria, Mauritania, Senegal
Stakeholders
Algeria - Ministry of Public Works and Transport
Start Date
Date Created Raw
Longitude
-0.000001