Central Corridor Transit Transport Facilitation Agency

By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.09
Project Status
Active
Project Stage
Construction
Completion Percentage
1
Sector Name
Transport
Subsector Name
Road
Alternative Names
Lot1: Kalundu port-Uvira-Luberizi (50 km)
Reference Plan
PIDA PAP 1
On SDM
On
Summary
Uvira-Bukavu road is an important missing link of the Central Corridor: Dar Es Salaam Port - Kigoma (Rail) - Kalundu Port (Lake Tanganyika) - Uvira - Bukavu (Road).
Upgrading of this missing link will facilitate trade and transport between Tanzania, Democratic Republic of Congo (DRC), Burundi and Rwanda. The road links two important lakes named Lake Tanganyika and Lake Kivu.
Description

Upgrading of the access road to the Port of Kigoma (Tanzania) by the Lake Tanganyika.

Capex Cost
0.00USD million
Preparation Cost
0.50
Operation Cost
0.00
Project Risk

<ul><li>None at this stage</li></ul>

Countries
Democratic Republic of Congo, Burundi, Democratic Republic of Congo, Rwanda, Tanzania, Burundi, Democratic Republic of Congo, Rwanda, Tanzania
Beneficiary Countries
Burundi, Democratic Republic of Congo, Rwanda, Tanzania
REC
CEEAC-ECCAS
Stakeholders
DRC - Roads Authority
Central Corridor Transit Transport Facilitation Agency
NEPAD Infrastructure Project Preparation Facility
Economic Community of Central African States
Central Corridor Transit Transport Facilitation Agency
NEPAD Infrastructure Project Preparation Facility
Email
ephrem.hailu@giz.de
Updated Date
Latitude
-2.960000
Longitude
29.010600
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.18
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of road from Urambo to Tabora (Tanzania).
Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Tanzania, Tanzania, Tanzania
Beneficiary Countries
Tanzania
REC
EAC
Stakeholders
East African Community
Tanzania National Roads Agency
Central Corridor Transit Transport Facilitation Agency
Email
ephrem.hailu@giz.de
Updated Date
Latitude
0.000000
Longitude
0.000000
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.19
Project Status
Completed
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of 85 km of single carriageway road from Tabora to Nyahua in Tanzania.
Description

<p>Upgrading of 85 km of single carriageway road from Tabora to Nyahua in Tanzania.</p>

Capex Cost
58.00USD million
Preparation Cost
6.00
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li></ul>

Countries
Tanzania, Tanzania, Tanzania
Beneficiary Countries
Tanzania
REC
EAC
Stakeholders
East African Community
Tanzania National Roads Agency
Central Corridor Transit Transport Facilitation Agency
Email
ephrem.hailu@giz.de
Updated Date
Latitude
-5.170000
Longitude
33.131500
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.21
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of road from Nzega to Tabora (Tanzania).
Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Tanzania, Tanzania, Tanzania
Beneficiary Countries
Tanzania
REC
EAC
Stakeholders
East African Community
Tanzania National Roads Agency
Central Corridor Transit Transport Facilitation Agency
Email
ephrem.hailu@giz.de
Updated Date
Latitude
0.000000
Longitude
0.000000
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.16
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of 209 km of single carriageway road between Nyahua-Chaya, Urambo-Kaliua, Kazirambwa-Chagu and Malagarasi-Uvinza in Tanzania.
Description

<p>The project involves upgrading of missing links along part of the Central Corridor of Manyoni-Itigi-Tabora-Urambo-Kaliua-Kigoma: Nyahua to Chaya (90km), Urambo to Kaliua (33km), Kazirambwa to Chagu (40km) and Malagarasi to Uvinza (51km) from gravel to paved.</p>

Capex Cost
171.00USD million
Preparation Cost
17.00
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: None Social Risks: None Socio-Enviro Classification: C - minimal social and environmental impacts Other External Risks: Not Reported</li></ul>

Countries
Tanzania, Tanzania, Tanzania
Beneficiary Countries
Tanzania
REC
EAC
Stakeholders
East African Community
Tanzania National Roads Agency
Central Corridor Transit Transport Facilitation Agency
Email
ephremg@nepad.org
Updated Date
Latitude
-5.210000
Longitude
31.880500
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.02.03
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Border Post
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of Mutukula One-Stop Border Post between Tanzania and Uganda, which lies on the Central corridor.
Description

<p>Construction of Mutukula One-Stop Border Post between Tanzania and Uganda. Border type: Juxtaposed.</p>

Capex Cost
14.51USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Tanzania, Uganda, Tanzania, Uganda, Tanzania, Uganda
Beneficiary Countries
Tanzania, Uganda
REC
EAC
Stakeholders
East African Community
Tanzania Revenue Authority
Uganda Revenue Authority
Central Corridor Transit Transport Facilitation Agency
TradeMark East Africa
TradeMark East Africa
Email
ephrem.hailu@giz.de
Updated Date
Latitude
-1.000000
Longitude
31.416600
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.10
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of 505 km of single carriageway road from Mpanda-Kasulu-Nyakanazi and Kasulu-Kigoma in Tanzania.
Description

<p>The project will enable a direct road link between the Central Corridor and Lake Victoria at Kigoma.</p>

Capex Cost
404.00USD million
Preparation Cost
40.00
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported</li></ul>

Countries
Tanzania, Tanzania, Tanzania
Beneficiary Countries
Tanzania
REC
EAC
Stakeholders
East African Community
Tanzania National Roads Agency
Central Corridor Transit Transport Facilitation Agency
Email
ephremg@nepad.org
Updated Date
Latitude
-4.690000
Longitude
30.426400
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.11
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of 252 km of single carriageway from Mpanda to Kanazi (Tanzania).
Description

<p>Upgrading of 252 km of single carriageway from Mpanda to Kanazi (Tanzania).</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Tanzania, Tanzania, Tanzania
Beneficiary Countries
Tanzania
REC
EAC
Stakeholders
East African Community
Tanzania National Roads Agency
Central Corridor Transit Transport Facilitation Agency
Email
ephrem.hailu@giz.de
Updated Date
Latitude
0.000000
Longitude
0.000000
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.17
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Bridge
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Upgrading of 48 km of approach roads and the Malagarasi bridge (Tanzania).
Description

<p>Upgrading of 48 km of approach roads and the Malagarasi bridge (Tanzania).</p>

Capex Cost
0.00USD million
Preparation Cost
0.00
Operation Cost
0.00
Countries
Tanzania, Tanzania, Tanzania
Beneficiary Countries
Tanzania
REC
EAC
Stakeholders
East African Community
Tanzania National Roads Agency
Central Corridor Transit Transport Facilitation Agency
Email
ephrem.hailu@giz.de
Updated Date
Latitude
0.000000
Longitude
0.000000
By Anonymous (not verified) , 24 February 2026
PIDA Code
T.08.03.25
Project Status
Active
Project Stage
Construction
Completion Percentage
0
Sector Name
Transport
Subsector Name
Road
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Rehabilitation of 91 km of single carriageway road between Lusahunga and Rusumo in Tanzania.
Description

<p>Rehabilitation of 91 km of single carriageway road between Lusahunga and Rusumo in Tanzania.</p>

Capex Cost
73.00USD million
Preparation Cost
7.00
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: Limited Social Risks: Not Reported Socio-Enviro Classification: C - minimal social and environmental impacts Other External Risks: Not Reported</li></ul>

Countries
Tanzania, Tanzania, Tanzania
Beneficiary Countries
Tanzania
REC
EAC
Stakeholders
East African Community
Tanzania National Roads Agency
Central Corridor Transit Transport Facilitation Agency
Email
ephrem.hailu@giz.de
Updated Date
Latitude
-2.600000
Longitude
30.890000