Organisation pour la Mise en Valeur du Fleuve Gambie

By Anonymous (not verified) , 24 February 2026
PIDA Code
E.07.01
Project Status
Active
Project Stage
Project Structuring
Completion Percentage
1
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of the Sambangalou Dam, with an installed capacity of 128 MW and a 3.8 km3 reservoir, which is a transboundary initiative of the Gambia River Basin Organisation (OMVG). The project involved four countries, namely The Gambia, Guinea, Guinea-Bissau and Senegal.

Description

<p>The proposed Sambangalou dam project entails the construction of a gravity dam, with a 128 MW capacity, and a 3.8 km3 reservoir. The dam is located in Senegal, 930 km upstream from the mouth of the Gambia river and about 25 km south of Kédougou. The reservoir overlaps Senegal and Guinea. The project now has two components, i.e. Sambangalou Dam and an interconnection transmission line which will link the Sambangalou and Kaleta dams to the electric grid of the four member countries.</p>

<p>The project was formerly part of larger OMVG Energy project involving fuoir countries (with Kaleta dam in Guinea and interconnecting power grid), however it split in 2011 after Guinea decided to develop Kaleta dam as a standalone.</p>

<p> </p>

Capex Cost
455.00USD million
Preparation Cost
23.00
Operation Cost
0.00
Project Risk

<ul><li> Environmental Risks: deteriorated water quality and fish yields downstream</li></ul>

Countries
Guinea, Senegal, Guinea, Senegal, Guinea, Senegal
Beneficiary Countries
Guinea, Senegal
REC
ECOWAS-CEDEAO
Stakeholders
Economic Community of West African States
Organisation pour la Mise en Valeur du Fleuve Gambie
African Development Bank
West Africa Power Pool
African Union Development Agency
World Bank
African Development Bank
Email
ephrem.hailu@giz.de
Updated Date
Latitude
12.370000
Longitude
-12.190100
By Anonymous (not verified) , 24 February 2026
PIDA Code
E.10.01
Project Status
Active
Project Stage
Project Structuring
Completion Percentage
1
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 1
On SDM
Off
Summary
Construction of 240 MW KalA©ta hydroelectric facility in on the KonkourA© River in west central in Guinea.
Description

<p>The proposed Kaléta dam project entails the construction of a gravity dam, with a 240 MW capacity. The Kaléta site is located in Guinea, 115 km northeast of Conakry and 130 km upstream of the mouth of the Konkouré River.</p>

<p>This project was previously part of the larger Gambia River Basin Development Organisation (OMVG) project involving the four countries, namely The Gambia, Guinea, Guinea-Bissau and Senegal. Guinea, however, decided to develop Kaléta as a stand-alone. Interconnection to other OMVG countries remains intended in future.</p>

<p>The project will have the following characteristics:</p>

<ul>
<li>Storage hydropower plant with 240 MW of hydropower capacity</li>
<li>Net average generation: 660 GWh/year</li>
<li>Gravity dam with maximum height: 22 m, crest length: 1060 m, reservoir storage: 23 million m3.</li>
</ul>

<p> </p>

Capex Cost
930.00USD million
Preparation Cost
47.00
Operation Cost
0.00
Project Risk

<ul><li>Country Risk: Political and economic stability are below continental average- rule of law, accountability and weak bureaucracy pose potential risks</li><li>Environmental Risk: 4500 inhabitants displaced</li></ul>

Countries
Guinea, Guinea, Guinea
Beneficiary Countries
Guinea
REC
ECOWAS-CEDEAO
Stakeholders
Economic Community of West African States
Guinea Ministry of Environment and Energy
West Africa Power Pool
Organisation pour la Mise en Valeur du Fleuve Gambie
African Union Development Agency
Email
ephrem.hailu@giz.de
Updated Date
Latitude
10.460000
Longitude
-13.276500